For the next week or so, crews will finish installing the storm improvements moving from the intersection of W Wash and Henry southeast down Henry. After that, a short section of water main on W Wash between Henry and Fairchild will be installed. What follows will be pavement and restoration work. We are still anticipating this project will be complete by October 11, 2024.
View past project updates »Project Details
Project Information
Project Overview
The overall project includes water and sanitary main replacements, pavement reconstruction, spot replacements of curb and gutter, sidewalk, and driveway aprons. It will also include improved pedestrian lighting.

Project Limits
West Washington Avenue from Broom Street to Fairchild Street
Henry Street from Main Street to West Washington Avenue
Project Schedule
Design: 2024
Construction: 2024
Business Resources
City's Road Reconstruction Business Guide
Public Involvement
There are a number of points of contact during this project where the public is encouraged to give feedback as part of public information meetings and public hearings. Dates, times and locations are indicated below:
Public Information Meetings
A public information meeting was held Jan. 31, 2024. The recording and presentation are available:
Jan. 31, 2024 Public Information Meeting Recording
City Process, Meetings
Board of Public Works: Feb. 21, 2024
Common Council: March 5, 2024
Mailings
Board of Public Works: Feb 7, 2024 Notice of Meeting Fact and Details Sheet Schedule of Assessments
Project Updates
September 4, 2024 Update
For the next week or so, crews will finish installing the storm improvements moving from the intersection of W Wash and Henry southeast down Henry. After that, a short section of water main on W Wash between Henry and Fairchild will be installed. What follows will be pavement and restoration work. We are still anticipating this project will be complete by October 11, 2024.
August 8, 2024 Update
Traffic has shifted to the northwest side of West Washington Avenue, with access to driveways on the southeast side of the street through the construction site. We will continue to have one lane in each direction divided by flexposts with a stop sign at Henry for pedestrians and construction traffic. This general configuration will stay the same for the remainder of the project. In the coming weeks, the contractor will finish installing water main on the northeast end of the project and then move southwest to complete sanitary and storm replacements.
August 8, 2024 Update
Traffic has shifted to the northwest side of West Washington Avenue, with
access to driveways on the southeast side of the street through the
construction site. We will continue to have one lane in each direction divided by flexposts with a stop sign at Henry for pedestrians and construction
traffic. This general configuration will stay the same for the remainder of the project. In the coming weeks, the contractor will finish installing water main on the northeast end of the project and then move southwest to complete sanitary and storm replacements.
May 31, 2024 Update
Work is scheduled to begin the week of June 2, 2024 on West Washington Avenue and Henry Street. Traffic will be shifted to the southeast side of West Washington Avenue as the project starts. Further updates will be posted as work progresses.
February 1, 2024 Update
Thank you to everyone who attended the Jan. 31, 2024 Public Information Meeting. The meeting materials are available:
Take this questionnaire by 4 p.m., Feb. 2, 2024: https://www.surveymonkey.com/r/KRP6DVT
Jan. 31, 2024 Public Information Meeting Recording
January 9, 2024 Update
The project design phase is in progress.
A public information meeting is scheduled for 6:30 p.m., Jan. 31, 2024, via Zoom. Registration prior is required.
Jan. 31, 2024 Public Information Meeting Registration
Take this questionnaire by 4 p.m., Feb. 2, 2024: https://www.surveymonkey.com/r/KRP6DVT