Pflaum Road
March 25, 2026 Update
The Pflaum Road construction project schedule is being updated to limit the impact on the schools.
2026 construction limits are Stoughton Road to Kvamme Lane.
Start of Construction: July 2026
Completion of Construction: November 2026
2027 construction limits are Kvamme Lane to Monona Drive.
Start of Construction: Spring 2027
Completion of Construction: August 2027
The project will be advertised for bid in April 2026.
The map of the project design overview is also updated.
Project Details
Project Information
Project Overview
The City of Madison Engineering Division will reconstruct Pflaum Road from the Stoughton Road Frontage Road to Monona Drive. The project includes removing and replacing the existing asphalt pavement and road base, and adding a new 10-foot-wide grade-separated shared-use path along the north side of the road. This path will extend the entire length of the project and connect with the existing path along Monona Drive.
Additional work includes replacing the sanitary sewer main and laterals,
water main and laterals, storm sewer, curb and gutter, sidewalk, and drive aprons as needed. MG&E will also replace the gas main prior to the start of street reconstruction.
Project Design Overview
Project Limits
Pflaum Road: Monona Dr to Stoughton Rd
Project Schedule
Approving Plans Specifications: April 2, 2025
The construction of Pflaum Road will be split into two parts to try and limit the impact on the schools.
2026 construction limits: Stoughton Road to Kvamme Lane
Start Construction: July 2026
Complete Construction: November 2026
2027 construction limits: Kvamme Lane to Monona Drive
Start Construction: Spring 2027
Complete Construction: August 2027
There are a number of points of contact during this project where the public is encouraged to give feedback as part of public information meetings and public hearings. Dates, times and locations are indicated below:
Public Information Meetings
- Aug. 28, 2025 Public Information Meeting Recording
- Aug. 28, 2025 Public Information Meeting PowerPoint Presentation
- March 12, 2025 Public Information Meeting Recording
- March 12, 2025 Public Information Meeting PowerPoint Presentation
Questionnaire
Please complete the project questionnaire by 12 p.m., Oct. 1, 2025.
Pflaum Road Questionnaire
City Process, Meetings
Common Council April 15, 2025
Board of Public Works April 2, 2025
Mailings
Board of Public Works: April 2, 2025 Notice of Meeting Fact and Details Sheet Schedule of Assessments
Business Resources
City of Madison Business Resources Guide for Road Construction
Project Updates
March 25, 2026 Update
The Pflaum Road construction project schedule is being updated to limit the impact on the schools.
2026 construction limits are Stoughton Road to Kvamme Lane.
Start of Construction: July 2026
Completion of Construction: November 2026
2027 construction limits are Kvamme Lane to Monona Drive.
Start of Construction: Spring 2027
Completion of Construction: August 2027
The project will be advertised for bid in April 2026.
The map of the project design overview is also updated.
August 29, 2025 Update
Thank you to everyone who attended the Aug. 28, 2025 Public Information Meeting. The meeting materials are now available:
- Aug. 28, 2025 Public Information Meeting Recording
- Aug. 28, 2025 Public Information Meeting PowerPoint Presentation
Also, please complete the project questionnaire by 12 p.m., Oct. 1, 2025.
Pflaum Road Questionnaire
August 22, 2025 Update
Questionnaire
Please complete the project questionnaire by 12 p.m., Oct. 1, 2025.
Pflaum Road Questionnaire
August 6, 2025 Update
A public information meeting is scheduled for 6 p.m., Aug. 28, 2025, via Zoom. Registration prior is required.
Aug. 28, 2025 Public Information Meeting Registration
April 25, 2025 Update
City Engineering is currently evaluating new geometric designs for Pflaum Road, which is part of the All Ages and Abilities bike network. As part of this project, we’re exploring opportunities to improve bicycle facilities along the route and make it safer and more accessible for all users. Once the geometric review is complete, we will host another Public Information Meeting (PIM) to share the findings and gather community feedback. The proposed changes will also be presented to the Transportation Commission (TC) for discussion and feedback.
March 13, 2025 Update
Thank you to everyone who attended the March 12, 2025 Public Information Meeting. The meeting materials are now available:
March 12, 2025 Public Information Meeting Recording
March 12, 2025 Public Information Meeting PowerPoint Presentation
March 12, 2025 Update
Join us tonight! Reminder:
There is a public information meeting scheduled for 6:30 p.m., March 12, 2025, via Zoom. Registration is required prior.
March 12, 2025 Public Information Meeting Registration
March 12, 2025 Public Information Meeting PowerPoint Presentation
February 27, 2025 Update
Plans and Specifications and authorizing the Board of Public Works to advertise the project will be presented at the BPW meeting on April 2, 2025.
There is a public information meeting scheduled for 6:30 p.m., March 12, 2025, via Zoom. Registration is required prior.
March 12, 2025 Public Information Meeting Registration