Quarter 3 2026 Update
Construction has started on the PV arrays. All modules have been installed on the maintenance building roof (3829) and the GreenPower crew is working on wiring the system. The roof replacement for the storage building (3901) is complete and the GreenPower crew will start installing racking and modules this month. 

New PV arrays installed on the roof of a gray metal building.  A Metro bus is parked at the front side.
PV arrays installed on the roof of 3829 Hanson Rd. Metro maintenance building.
A view while standing on temporary plywood sheeting walkway overlooking the newly installed black EPDM roof.
Roof replacement before PV array installation at 3901 Hanson Rd. Metro storage building.

 

View past project updates »

Project Details

Location

  • 3829 Hanson Rd, Madison, WI 53704
    Madison, WI 53704
  • 3901 Hanson Rd, Madison, WI 53704
    Madison, WI 53704

Project Type

Status

In Design

Estimated Schedule

Alder District

  • District 17

Project Information

Project Overview

This project will install 1,200 kW of solar electric (PV) panels on two buildings at the Metro Hanson Road Satellite Bus Facility. When complete the arrays will generate ~1,530,000 kWh of electricity per year reducing operational costs for Metro. The array will be installed by the Engineering Division’s GreenPower program where trainees with little to no electrical skills are provided on-the-job training through solar installations on City buildings.

Project Schedule

City User Agency: Madison Metro

Planning and Design: Quarter 2 2025 through Quarter 1 2026

Construction Start Date: Quarter 2 2026

Expected Completion Date: Quarter 4 2026

Project Updates

July 13, 2026 Update

Quarter 3 2026 Update
Construction has started on the PV arrays. All modules have been installed on the maintenance building roof (3829) and the GreenPower crew is working on wiring the system. The roof replacement for the storage building (3901) is complete and the GreenPower crew will start installing racking and modules this month. 

New PV arrays installed on the roof of a gray metal building.  A Metro bus is parked at the front side.
PV arrays installed on the roof of 3829 Hanson Rd. Metro maintenance building.
A view while standing on temporary plywood sheeting walkway overlooking the newly installed black EPDM roof.
Roof replacement before PV array installation at 3901 Hanson Rd. Metro storage building.

 

January 22, 2026 Update

Quarter 1 2026 Update
Project planning and material procurement is underway. The Engineering Division’s GreenPower installation crew will start working onsite in late spring. 3901 Hanson Road’s roof is being replaced ahead of this project through a purchase of service contract.