Tenney Park Ferry Building Rehabilitation
November 19, 2026 Update
An Advertisement for Bid was released for Ferry Building Lead Abatement on November 18, 2026. RFB #15084-0-2026-AH is available only on VendorNet and Euna OpenBids (Demand Star). Two pre-bid building tours for interested bidders are scheduled for Monday, November 23, 2026 at 1:00 p.m. and Monday, November 30, 2026 at 9:00 a.m. at the project site, 471 Marston Ave., Madison WI.
View past project updates »Project Details
Project Information
Project Overview
The scope of work for the Tenney Park Ferry Building Rehabilitation project includes, but is not limited to, the removal of the repair or replacement of deteriorated wood in kind, painting, replacing doors, repairing exterior cracks in concrete walls, installing plexiglass windows in wood frames in existing boarded openings and a full roof replacement.
Project Schedule
City User Agency: City of Madison Parks
Planning and Design: In progress Quarter 1 2026
Construction and Bid Doc Preparation: Quarter 1 2027
Advertisement for Bid for Lead Abatement: November 18, 2026
RFB #15084-0-2026-AH is available only on VendorNet and Euna OpenBids (Demand Star).
Pre-Bid Site Visits: Monday, November 23, 2026 at 1:00 p.m. and Monday, November 30, 2026 at 9:00 a.m. at the project site, 471 Marston Ave., Madison WI.
Bid Due: December 4, 2026
"All information regarding dates/times/locations are informational and should be verified with official bidding documents posted on the above sites."
1st Advertisement of Rehabilitation Bid: TBD available only on Bid Express
Contractor's Bid Talk (Virtual): TBD
Bid Due Date: TBD
Construction Start Date: TBD
Expected Completion Date: TBD
"All information regarding dates/times/locations are informational and should be verified with official bidding documents posted on Bid Express."
Public Involvement
There are a number of points of contact during this project where the public is encouraged to give feedback as part of public information meetings and public hearings. Dates, times and locations will be indicated below as this project progresses.
Public Information Meetings
TBD
City Process Meetings
TBD
Project Updates
November 19, 2026 Update
An Advertisement for Bid was released for Ferry Building Lead Abatement on November 18, 2026. RFB #15084-0-2026-AH is available only on VendorNet and Euna OpenBids (Demand Star). Two pre-bid building tours for interested bidders are scheduled for Monday, November 23, 2026 at 1:00 p.m. and Monday, November 30, 2026 at 9:00 a.m. at the project site, 471 Marston Ave., Madison WI.
October 16, 2026 Update
Quarter 4 2026 Update
Facilities staff is working to complete construction documents and specifications in early 2027.
July 9, 2026 Update
Quarter 3 2026 Update
Facilities staff is working to complete construction documents and specifications in late 2026.
April 15, 2026 Update
Quarter 2 2026 Update
The project scope remains unchanged. Facilities staff have been unable to make progress on this project in early 2026 and are planning to complete the construction documents in late 2026 to bid in early 2027 and complete the work in the spring/summer of 2027.