Campbell Street - Vilas Avenue
Last Updated: 10/12/2020
Latest Update
9/10/2020:
This project is on schedule. Crews have finished installing new storm and sanitary sewer main and laterals. Crews have finished installing roadway base and concrete curb and gutter. Crews have started installation of boulder wall around Bear Mound Park and will schedule final asphalt paving and restoration after.
Project Overview
This project includes the asphalt pavement reconstruction of Vilas Avenue between Garfield Street and the east side of Bear Mound Park and Campbell Street from Vilas Avenue to Drake Street. Spot repairs of curb and gutter, sidewalk, and driveway aprons will be included with this project, as well as utility replacements of storm sewer and sanitary sewer.
Project Limits
Vilas Avenue - Garfield Street to east end of Bear Mound Park (both legs)
Campbell Street - Vilas Avenue to Drake Street
Project Schedule
Construction begins: July 27, 2020
Scheduled Completion: Oct. 16, 2020
Public Involvement
There are a number of points of contact during this project where the public is encouraged to give feedback as part of public information meetings and public hearings. Dates and times are indicated below:
Public Information Meetings
A public information meeting was held Dec. 13, 2018.
Dec. 13, 2018 Public Information Meeting PowerPoint Presentation
City Meetings, Process
Board of Public Works: Nov. 20, 2019
Common Council: May 19, 2020