Cannonball Path Phase 6
Latest Update
3/10/2022 Update:
The project team is currently working on the design and permitting of the path and new bridge over Wingra Creek, along with starting the real estate process and coordinating with the adjacent property owners on the necessary easements. We anticipate that a public informational meeting will be held in the spring/summer of 2022.
Project Overview
This project is a shared-use (bicycle and pedestrian) path that extends the existing Cannonball Path at Fish Hatchery Road to the Wingra Creek Path.
This is the final piece of the overall four-mile Cannonball Path linking areas of Fitchburg and Arbor Hills neighborhood with downtown Madison. The overall Cannonball Path project is a joint effort between Madison and Fitchburg, with land acquisition partially funded by Wisconsin Department of Natural Resources. Madison is the lead agency for the project from the west line of the Arbor Hills neighborhood to its northern terminus.
The Cannonball Path connects neighborhoods with parks, schools, major conservancy areas as well as retail, commercial and employment centers. It also connects to the Capital City Trail, Southwest Path, Military Ridge Trail and Badger State Trail, making it a key component of the regional network of paths for recreation as well as transportation.
In 2020, the City plans to apply for grant funds to help fund the future construction of this path. The City is reviewing possible route alternatives to make the connection between the current end of the path at Fish Hatchery Rd. to the Wingra Creek Path.
Two alternatives have been considered for how to extend the Cannonball Path. One alternative is to remove the on-street bike lane and sidewalk on one side of Fish Hatchery Rd. in order to install a multi-use path on that side of the street. This path would be at the same grade as the existing sidewalk. The second alternative is to continue working on a route parallel to the railroad tracks and then head north through Bowman Park to connect to Plaenert Drive. These alternatives are depicted in the following map: Alternatives Map
After receiving input at the public informational meeting (see below) and through additional correspondence, the current preferred alternative is the off-street route, which would extend along the railroad tracks and then north through Bowman Park.
Project Limits
Information will be posted when available.
Project Schedule
Project construction is currently scheduled for 2022.
Public Involvement
There are a number of points of contact during this project where the public is encouraged to give feedback as part of public information meetings and public hearings. Dates and times are indicated below:
Public Information Meetings
A public information meeting was held Dec. 4, 2019 at Wright Middle School, Library Media Center, 1717, Fish Hatchery Road, Madison, WI.
Dec. 4, 2019 Public Information Meeting PowerPoint Presentation
City Meetings, Process
More information will be posted when available.