Update: July 5, 2017
"Bidding" status

1st Advertisement of Bids: June 30, 2017 available on Bid Express.
Bid Due Date: August 11, 2017
Pre-Bid Contractors Meeting: Wednesday, July 26, 2017 from 8:30 -10:30 AM (Please meet in the City-County Building (CCB) at 210 Martin Luther King Jr. Blvd. Conference room 118).
SBE Pre-Bid Meeting: July 28, 2017 1:00 pm at 1600 Emil St., Madison, WI
"All information regarding dates/times/locations are informational and should be verified with official bidding documents posted on Bid Express."
City User Agency:  Parking Utilities
1st Advertisement of Bids: June 30, 2017
Bid Due Date:  August 11, 2017
Construction Start Date: October 02, 2017

Project History:

May 16, 2017  File #46812
Capitol East Parking Garage 2017 Budget Amendment

May 10, 2017  File #46095
Urban Design Commission Initial/Final Approval Application

April 18, 2017 File #46812
Capitol East Parking Garage 2017 Budget Amendment

Jan. 31, 2017   Public Open House
Community Open House focused on the design of the Parking Structure.

January 5, 2017  The Capital Times article
Board of Public Works approves Capitol East Parking Garage

November 1, 2016 File #44762
Resolution for a Development Agreement of the “Spark” project, the “Cosmos” project, and the Capitol East District Parking Structure and a contract with Graef-USA Inc. to complete architecture/engineering for a Capitol East District Parking Structure.

September 6, 2016 File #42270
Resolution for contract with Graef-USA Inc. for architecture/engineering services. 
 
March 21, 2016 File #42203
Update on 800 East Washington south block projects and Capitol East Parking Structure. 

February 2, 2016 File #41172
Resolution to issue a Request for Proposals for architectural and engineering services.