Mendota-Grassman Greenway Flood Mitigation and Restoration Design
April 16, 2024 Update
The Mendota Grassman Greenway project is underway! This winter the contractor worked on grading the greenway and building the sanitary maintenance access paths. As sections of the greenway were graded, a restoration contractor put down native seed and erosion matting to hold the soil in place. Later this spring trees and shrubs will be planted. The final sections of the greenway that are adjacent to the culverts on Camelot Dr and University Ave will be graded and restored with native seed and matting following the installation of the culverts. Until then, water will pool in the greenway behind the culverts. Once the culverts are installed the greenway should flow more efficiently to the lake.
The Camelot Drive culvert is currently under construction. The construction on University Ave will begin once Camelot Dr culvert is finished (likely sometime between mid-May and the start of June).
For an overview of the project goals and purpose please view the Oct. 3, 2022 Public Information Meeting PowerPoint Presentation or watch the Oct. 3, 2022 Public Information Meeting Recording
For a summary of the restoration plans please see the Habitat Stewardship Subcommittee Presentation Slides
View past project updates »Project Details
Project Information
Overview
The City of Madison, like many communities, has seen a recent increase in extreme flood events. This increase has occurred most notably in Madison since 2016, when a large and intense rain event in late July caused extensive flooding of public and private property on Madison’s west side. Large events in July 2017 and June 2018 caused similar flooding, again largely focused on Madison’s west side.
On August 20, 2018, Dane County experienced an unusual precipitation event that caused flooding in excess of that seen in any of the prior events mentioned. Rain gages monitoring that event registered between 8-10” of precipitation on its west side over (approximately) a 12-hr period. Many of Madison’s west side neighborhoods experienced flash flooding, resulting in millions of dollars in property damage.
In response to the damage incurred, as well as the likely increasing frequency of such events due to global climate change, the Madison Common Council authorized the City of Madison Engineering Division (City Engineering) to develop watershed models and plans for watersheds of greatest concern in the Madison area. The redesign of this greenway system is a solution resulting from of one of these studies.
In the spring of 2021 the City will finish a watershed study for the Stricker’s/Mendota watershed that encompasses this area. The purpose of that study is to evaluate existing conditions in the watershed and look for solutions for flood reduction. Homes adjacent to this greenway have repeatedly flooded in the past and the preliminary proposed solutions for this watershed study indicate the best solution for this area is to maximize conveyance.Due to the chronic flooding in this neighborhood, the fact that the City had budgeted a project in this greenway prior to the watershed study, and the minimal variables that could impact the design possibilities as the watershed study refines the solutions, the City has decided to hire a consultant to work on the design of this greenway in earnest. The City of Madison has hired MSA complete the flood mitigation and restoration design starting in December of 2020.
Project Limits
View full Mendota Grassman Greenway System Project Area map.
Along the greenway that runs southwest to northeast from Old Middleton Road to Lake Mendota.
Between Baker Avenue and Heim/Camelot Drive
Restoration and Tree Removals
The City has been approved for a tree removal permit. Below please find additional information about the tree removal and restoration plan:
- Tree Removal Plan Overview
- Habitat Stewardship Subcommittee Presentation Slides (showing updated tree removal data from the public information meeting #2 and a draft restoration plans)
- For more background, please watch the recording of the Public Information Meeting #2 from 31:30 to 1:04:00. This is a detailed presentation on draft tree removal plan and restoration plans for the greenway.
- Ecological Restoration in Stormwater Ponds and Greenways Story Map
- Tree removal plan sheets
- Tree Inventory in Project Area
- Draft Restoration Plan
Project Schedule
The project will be under construction in 2023-2024 with restoration efforts continuing into 2025.
Public Involvement
There are a number of points of contact during this project where the public is encouraged to give feedback as part of public information meetings and public hearings. Dates, times and locations are indicated below:
Public Information Meetings
Oct. 3, 2022 Public Information Meeting Recording
Oct. 3, 2022 Public Information Meeting PowerPoint Presentation
May 25, 2021 Public Information Meeting Recording
May 25, 2021 Public Information Meeting PowerPoint Presentation
City Process, Meetings
Board of Public Works: March 8, 2023
Common Council: March 21, 2023
*Note: Registering to speak is only necessary for Common Council and Board of Public Works Meetings. You do not need to register to speak at Public Information Meetings. Simply attend with registration, and you'll have an opportunity to share feedback and ask questions.
Learn more about attending and speaking at the public hearings virtually.
Watch Meetings Online
City Meeting Schedule