Last Updated: 05/25/2022

Project Overview

Installation of a roughly 25 kW solar photovoltaic system at Madison Fire Department Station 08. The system will consist of roof mounted modules and will produce an estimated 32,500 kWh per year. Once completed 34% of the building’s electricity usage will be generated by the solar array.

Project Schedule

City User Agency: City of Madison Fire
Design and Planning: June 2022
1st Advertisement of Bid: July 07, 2022
Bid Due Date: August 04, 2022
Construction Start Date: September 2022
Expected Completion Date: December 2023

"All information regarding dates/times/locations are informational and should be verified with official bidding documents posted on Bid Express."

Public Involvement

There are a number of points of contact during this project where the public is encouraged to give feedback as part of public information meetings and public hearings. Dates, times and locations are indicated below:

City Process Meetings

June 07, 2022 Common Council File #71639
May 25, 2022 Board of Public Works File #71639
Approving plans and specifications and authorizing the Board of Public Works to advertise and receive bids for Solar PV - Fire Station 08