Solar PV – Fire Station 08
Project Details
Project Information
Latest Update
October 04, 2023
Project status: Completed
Project Overview
Installation of a roughly 25 kW solar photovoltaic system at Madison Fire Department Station 08. The system will consist of roof mounted modules and will produce an estimated 32,500 kWh per year. Once completed 34% of the building’s electricity usage will be generated by the solar array. The array will be installed by the Engineering Division’s GreenPower program where trainees with little to no electrical skills are provide on-the-job training through solar installations on City buildings.
Project Schedule
City User Agency: City of Madison Fire
Design and Planning: June 2022
1st Advertisement of Bid: N/A
Bid Due Date: N/A
Construction Start Date: November 2022
Expected Completion Date: August 2023