This project is complete. This information is available for reference purposes.January 6, 2025 Update
Quarter 1 2025 Update
The building is substantially complete with the exception of test and balancing of the HVAC system, fire alarm testing, and final lighting installation. The final inspections for occupancy will be scheduled for early February 2025 and the project is expected to be turned over the Parks shortly after. Opening date to be determined. Please look for a further update later in Quarter 1 on opening information.
View the project's Flickr album for photos.
View past project updates »Project Details
Project Information
Project Overview
The Door Creek Park Shelter, located in Door Creek Park, will provide a quality parks facility experience to the Door Creek neighborhood and Madison community. The shelter's primary function will be as a year round-space for community and private events. For more information about this project and for Public Information meetings on this project, please visit City of Madison Parks: Door Creek Park Shelter
View live images of the project on the construction site camera and photos on the project's Flickr album.
October 04, 2023
The bid for the project to construct the new shelter was opened 6/22/23 and was awarded through Board of Public Works and Common Council in late July to C.G. Schmidt. Inc. A Start Work letter was issued on 8/21/2023 and the contractor will be closing out 2023 with submittals and subcontractor qualifications. Work is anticipated to begin in spring of 2024.
Project Schedule
City User Agency: Madison Parks
Design and Planning: April 2021 - August 2022Advertisement of Bid: May 12, 2023, available only on Bid Express
Bid Talk (Virtual): June 07, 2023 @ 11:00 a.m.
June 7, 2023 Bid Talk: Door Creek Shelter Recording
June 7, 2023 Bid Talk: PowerPoint Presentation
Bid Due date: June 22, 2023
Construction Start: Spring 2024
Completion: February 28, 2025
"All information regarding dates/times/locations are informational and should be verified with official bidding documents posted on Bid Express."
Public Involvement
There are a number of points of contact during this project where the public is encouraged to give feedback as part of public information meetings and public hearings. Dates, times and locations are indicated below:
City Process Meetings
Jul. 25, 2023 Common Council File #78611
Jul. 19, 2023 Board of Public Works File #78611
Awarding Public Works Contract No. 9326, Door Creek Park Shelter
Jan. 17, 2023 Common Council File #75279
Jan. 04, 2023 Board of Public Works File #75279
Amending the 2023 Capital Budget for Parks Division for the Door Creek Park Shelter project and approving plans and specifications for Public Works bidding
Sept. 20, 2022 Common Council File #73517
Sept. 07, 2022 Board of Public Works File #73517
Authorizing the Mayor and City Clerk to execute an amendment to the existing Purchase of Services contract (Architect) between the City of Madison and Aro Eberle Architects to provide professional architectural and engineering design services and construction administration services for the design and construction of the Door Creek Park Shelter
April 03, 2020 File #59941
Enter into a contract for Purchase of Services (Architect) with Aro Eberle Architects to provide professional architectural and engineering design services and construction administration service
Dec.12, 2019 RFP #8860-0-2019-BP
Soliciting proposals from qualified vendors for Architect and Engineering Services for Door Creek Shelter
Project Updates
January 6, 2025 Update
Quarter 1 2025 Update
The building is substantially complete with the exception of test and balancing of the HVAC system, fire alarm testing, and final lighting installation. The final inspections for occupancy will be scheduled for early February 2025 and the project is expected to be turned over the Parks shortly after. Opening date to be determined. Please look for a further update later in Quarter 1 on opening information.
View the project's Flickr album for photos.
October 18, 2024 Update
Quarter 4 Update
Masonry walls and building steel are fully installed. Contractor is currently installing standing seam roof as well as doors and windows. Work continues on interior mechanical, electric, and plumbing systems. Work will begin on interior finishes once building enclosure is complete. Work has started on new islands and light poles for parking lot and contractor is preparing for final site work around the shelter.
View live images of the project on the construction site camera.
July 1, 2024 Update
Quarter 3 Update
Building foundations and slab on grade are complete. The contractor has started installing masonry walls and building steel. Roof installation will begin next month. Completion is expected by mid-January 2025.
View live images of the project on the construction site camera.
May 15, 2024 Update
The Contractor has mobilized to the site. Please note that the existing sports courts, playgrounds, and paths are still accessible. The public should follow all signage and be cautious of construction vehicles.
The project currently focuses on building foundations and underground utilities. By the end of the month the slab on grade is scheduled to be poured. Construction of the structure will start in June and run through the summer.
View live images of the project on the construction site camera.
April 1, 2024 Update
Quarter 2 Update
Onsite construction activities for the new Door Creek Park Shelter are anticipated to begin the week of April 8th, 2024. Construction is expected to be completed by December 2024.