Fordem Avenue Sanitary Sewer Replacement

Archived Project

This project is complete. This information is available for reference.
If you need an accessible version of this content, please report an accessibility issue.

August 31, 2022 Update

On Sept. 1, the Contractor will be installing asphalt pavement to areas disturbed by construction. After discussions between the City, the Contractor and with the Property Management group it was determined that it would be best to complete this work in one day. Parking will be closed through the entire project area, to allow this work to be completed in one day. Parking will be opened to residents ASAP but closures are likely to last all day on Sept. 1. 

View past project updates »

Project Details

Location

1622 Fordem Avenue
Madison, WI 53704

Status

Completed

Estimated Schedule

Impact

Minor

Alder District

  • District 2

Contract Number

Project Information

Project Overview

This project will replace aging and deteriorating sanitary sewer main in the parking lot of 1622 Fordem Avenue. The existing sanitary sewer has structural and operational issues that make removing and replacing the sanitary sewer a necessity.

Project Limits

Map of project limit

Project Schedule

BPW Approving Plans and Specifications: 11/3/2021
CC Approving Plans and Specifications: 11/16/2021
First Advertisement for Bids: 11/18/2021
Receive Bids: 12/2/2021
Approximate Start of Construction: 4/1/2022

Public Involvement

There are a number of points of contact during this project where the public is encouraged to give feedback as part of public information meetings and public hearings. Dates, times and locations are indicated below:

Public Information Meetings

Oct. 28, 2021 Public Information Meeting Recording

Oct. 28, 2021 Public Information Meeting PowerPoint Presentation

City Process, Meetings

Common Council: Nov. 16, 2021
Board of Public Works: Nov. 3, 2021
Public Information Meeting: Oct. 28, 2021

Mailings

Start Work Letter and Fact Sheet

Project Updates

August 31, 2022 Update

On Sept. 1, the Contractor will be installing asphalt pavement to areas disturbed by construction. After discussions between the City, the Contractor and with the Property Management group it was determined that it would be best to complete this work in one day. Parking will be closed through the entire project area, to allow this work to be completed in one day. Parking will be opened to residents ASAP but closures are likely to last all day on Sept. 1. 