E Main Street and S Hancock Street Resurfacing
July 25, 2025 Update
MGE’s contractor, Intercon, will begin work on Main Street, Monday, July 28. They will be starting mid-block between Butler and Hancock, heading toward the Hancock intersection. There will not be on-street parking on the north side of Main Street in this area. Parking stalls will open up as work progresses.
Listed below are the contacts for MGE and Intercon:
MGE Project Manager: Matt Colvin
872-223-2637, matt.colvin@mge.com
MGE Contractor Project Manager: Chris Quam
608-695-5871, cquam@intercon-const.com
View past project updates »Project Details
Project Information
Project Overview
The City is planning construction of E Main St from S Webster St to S Blair St and S Hancock St from East Washington Ave to south of E Wilson St in 2025. The project improvements include replacement of existing pavement and pavement base, sections of curb and gutter, sections of sanitary sewer main and laterals, storm sewer, and water main. Damaged sections of sidewalk will also be replaced or as needed to install sewer service laterals. Additionally, Madison Gas & Electric (MGE) will be replacing the electric duct bank on E Main St. This work will begin under a permit in Spring 2025.
Project Limits
E Main St - S Webster St to S Blair St
S Hancock St - East Washington Ave to south of E Wilson St
Project Schedule
Start of MGE Construction – May, 2025 (tentative)
Start of City Construction – August, 2025 (tentative)
End of City Construction – June, 2026 (tentative)
Public Involvement
There are a number of points of contact during this project where the public is encouraged to give feedback as part of public information meetings and public hearings. Dates, times and locations are indicated below:
Public Information Meetings
March 4, 2025 Public Information Meeting PowerPoint Presentation
March 4, 2025 Public Information Meeting Recording
Project Questionnaire
A project questionnaire is now available. Please complete by 5 p.m., March 11, 2025.
East Main Street and S Hancock Street Resurfacing Questionnaire
City Process, Meetings
Board of Public Works – 4/2/2025 (tentative)
Common Council - 4/15/2025 (tentative)
Mailings
Board of Public Works: April 2, 2025 Notice of Meeting Fact and Details Sheet Schedule of Assessments