Davidson St, Park Ct, Maher Ave, and Gary St Reconstruction
July 28, 2025 Update
Board of Public Works Meeting
The Davidson St, Park Ct, Maher Ave and Gary St reconstruction is scheduled for construction starting in Spring 2026. The project will be presented to the Board of Public Works on August 6, 2025.Meeting information is available on the following link: https://www.cityofmadison.com/city-hall/committees/board-of-public-works/2025-08-06. Note: Registration for the meeting and the meeting agenda will become available closer to the meeting date.
A mailing detailing the project has also been sent out along with preliminary special assessments for the project. Any further information on assessments can be found here. https://www.cityofmadison.com/engineering/streets-paths/repairs-and-reconstruction/assessments-payment-plans
View past project updates »Project Details
Project Information
Project Overview
The City plans to reconstruct portions of Davidson St, Park Ct, Maher Ave, and Gary St. The proposed project would include replacement of the
sanitary sewer mains and laterals, water mains and laterals, installation of new storm sewer, and replacement of the asphalt pavement with new curb and gutter and sidewalk as approved. There are a variety of options that may be possible for how the street is reconstructed, and these options will be discussed at future public informational meetings and City committee meetings.
Project Limits
- Davidson St – Maher Ave to Dempsey Rd
- Park Ct – Maher Ave to Dempsey Rd
- Maher Ave – Cottage Grove Rd to Lake Edge Blvd
- Gary St - Dempsey Rd to Dead-End
Project Schedule
Anticipated bid date of summer 2025, with construction during the fall of 2025 and spring/summer 2026
Public Involvement
There are a number of points of contact during this project where the public is encouraged to give feedback as part of public information meetings and public hearings. Dates, times and locations are indicated below:
Public Information Meetings
- May 15, 2025 Public Information Meeting Recording
- May 15, 2025 Public Information Meeting PowerPoint Presentation
- March 26, 2025 Public Information Meeting PowerPoint Presentation
- March 26, 2025 Public Information Meeting Recording
Questionnaire
Please complete this second project questionnaire by 5 p.m., April 2, 2025.
Davidson Street, Park Court, Maher Avenue and Gary Street Reconstruction Questionnaire
City Process, Meetings
Transportation Commission 05/14/2025
B/media/210421oard of Public Works 06/04/2025
Common Council 06/17/2025
Mailings
Board of Works Letter, Fact & Detail & Assessment 08/06/2025
Project Updates
July 28, 2025 Update
Board of Public Works Meeting
The Davidson St, Park Ct, Maher Ave and Gary St reconstruction is scheduled for construction starting in Spring 2026. The project will be presented to the Board of Public Works on August 6, 2025.Meeting information is available on the following link: https://www.cityofmadison.com/city-hall/committees/board-of-public-works/2025-08-06. Note: Registration for the meeting and the meeting agenda will become available closer to the meeting date.
A mailing detailing the project has also been sent out along with preliminary special assessments for the project. Any further information on assessments can be found here. https://www.cityofmadison.com/engineering/streets-paths/repairs-and-reconstruction/assessments-payment-plans
June 9, 2025 Update
Transportation Commission Meeting
The Davidson St, Park Ct, Maher Ave and Gary St reconstruction is scheduled for construction in Fall 2026. The project will be presented to the Transportation Commission on June 11, 2025. Meeting information is available on the following link: https://www.cityofmadison.com/city-hall/committees/transportation-commission/2025-06-11. Note: Registration for the meeting and the meeting agenda will become available closer to the meeting date.
May 19, 2025 Update
Thank you to everyone who attended the May 15, 2025 Public Information Meeting. The meeting materials are now available.
May 15, 2025 Public Information Meeting Recording
May 15, 2025 Public Information Meeting PowerPoint Presentation
May 5, 2025 Update
The project limits have been extended on Gary St. The new limits are from Dempsey Rd to the dead-end, previous limits were from Dempsey Rd to Elinor St. Limits were updated for failing utilities found in the early design phase.
Following the design team’s review of the City’s Complete Green Street policy, along with input from the neighborhood at the first public information meeting, City staff have prepared street layout options that we would like your feedback on for Davidson St, Maher Ave, Park Ct and Gary St. Please note that this feedback will not be the ultimate decision on the street design, but it will be taken into consideration by the Transportation Commission, Board of Public Works, and Common Council, who are ultimately responsible for approving the final design.
A public information meeting is scheduled for 6 p.m., May 15, 2025, via Zoom. Registration prior is required.
May 15, 2025 Public Information Meeting Registration
Please complete this second project questionnaire by 5 p.m., May 30, 2025:
Davidson Street, Park Court, Maher Avenue and Gary Street Reconstruction Questionnaire
March 28, 2025 Update
Thank you to everyone who attended the March 26, 2025 Public Information Meeting. The meeting materials are now available:
March 26, 2025 Public Information Meeting PowerPoint Presentation
March 26, 2025 Public Information Meeting Recording
Questionnaire
Please complete the project questionnaire by 5 p.m., April 2, 2025.
Davidson Street, Park Court, Maher Avenue and Gary Street Reconstruction Questionnaire
March 10, 2025 Update
A public information meeting is scheduled for 6 p.m., March 26, 2025, via Zoom. Registration prior is required.
March 26, 2025 Public Information Meeting Registration
Please complete the project questionnaire by 5 p.m., April 2, 2025.
Davidson Street, Park Court, Maher Avenue and Gary Street Reconstruction Questionnaire
March 6, 2025 Update
The project is currently in the planning stages. A virtual public information meeting will be held to inform the residents of the initial improvements and will be able to give their feedback. The date of the meeting will be Wednesday, March 26. A second public information meeting to give more details on the improvements based on findings and feedback will be held, but the date is to be determined.