Anderson Street

Last Updated: 02/14/2020

Project Overview:

The proposed project is a street resurfacing that will include replacement of existing pavement and storm sewer. In addition, the proposed project will include the installation of new sidewalk and bicycle facilities on the south side of Anderson Street from Wright Street to North Stoughton Road.

Project Limits

Anderson Street from Wright Street to North Stoughton Road

Project Schedule:

Design:  1/1/2020 to 6/1/2020
Construction:  6/1/2020 to 8/28/2020

Public Involvement:

There are a number of opportunities during this project where the public is encouraged to give feedback as part of public information meetings and public hearings. Dates, times and locations are indicated below:

Common Council:  Anticipated in Spring 2020

Board of Public Works: Anticipated in Spring 2020

Public Information Meetings: 

February 11, 2020
The City is held a public information meeting on this project on Feb. 11, 2020. The presentation and the two design options shared at the meeting are below:
PIM Presentation
Option 1
Option 2