Last Updated: 04/21/2017

New Fire Station

Fire Station 14, located near the intersection of Dairy Drive and Femrite Drive in Madison, Wisconsin, will provide space to house, up to a double company and medical unit. A community room with adjoining toilet room will be programmed for staff and public use. The target building size is approximately 14,000 – 20,000 SF and the target construction cost is approximately $4,200,000 to $6,000,000.

A standard City of Madison fire station is 14,000 SF. The Pre-Design process for Fire Station 14 indentified an additional 6,000 SF, that would bring the building total to 20,000 SF, that includes a larger community room and an expanded indoor area to conduct Recruit PAT’s (Physical Ability Test), Incumbent Standards and other training evolutions. Integrating a larger community space into the Fire Station 14 design addresses deficiencies in the area and brings opportunities for community meetings, engagement, education, fire prevention, health services (community paramedicine), and more to be brought into the community. In addition, the Madison Fire Department currently doesn’t have dedicated space for recruit testing, incumbent standards or training evolutions. The lack of dedicated space for training, Recruit PAT’s, Standards evaluations increases operational costs to the Madison Fire Department and has resulted in legal issues when hiring new recruits and evaluating existing employees. The addition of this space is currently under review by the City.

A public informational meeting is scheduled at Fire Station 5 (4418 Cottage Grove Rd, Madison, WI 53716) on May 8 from 6:30pm - 8pm. The project architect, OPN Architects, will have a short overview presentation and key staff from the Fire Department and City Engineering along with Alder Denise DeMarb will be available to answer questions about the project.


City User Agency:  Madison Fire Department
Planning and Design: 2017
     Jan. 2017: In final contract negotiations with the architect to start design.
     Feb 2017: Hired OPN Architects and KJWW Engineering to design fire station.
     Feb 2017: Hired McKinstry for energy modeling and commissioning to meet LEED requirements for fire station.
     Feb. – April 2017: Completed Pre-Design – site plan, programming and floor plan.
Construction: Early 2018
Expected Completion: Late 2018
Public Works Contract: TBD

LEED Goals:  LEEDv3 New Construction – target is LEEDNCv3 Silver


Preliminary Exterior Design of Proposed Fire Station 14
(subject to change during the next phase of the design process)
FS14 Preliminary Exterior


Project History:

April 4, 2017
Engineering Q1 Update to Mayor Soglin, Common Council Alders
 

February 7, 2017  File #45664
Architect Authorization of Purchase of Service Contract

November 2016
2017 Capital Budget Amendments (Page 1,12,13 Covers Fire Station 14)

November 18, 2016 Alder DeMarb's Updates
Update for District 16 regarding Fire Station 14
 

February 24, 2015 File #36850
Resolution passed for Architect/Engineer Master Site Planning Design Services

February 19, 2015 Public Meeting
Community stakeholders wanted public space in the building. The building will be designed to include a community room.