Starker Avenue Resurfacing with Utilities
July 24, 2025 Update
The Contractor has completed all underground utility installations and concrete work throughout the project. Soil restoration is scheduled for completion this week, weather permitting.
Final grading will begin shortly in preparation for asphalt paving. Street paving is expected to take place within the next three weeks.
The project remains on schedule for completion by the end of August 2025.
The Construction Inspector, Paul Lauby, 608-520-2378, plauby@cityofmadison.com will be the best on-site contact throughout construction.
View past project updates »Project Details
Project Information
Project Overview
The City is planning to resurface Starker Avenue from Woodvale Drive to Droster Road. The project includes replacing the sanitary sewer and laterals, water main, storm sewer main and inlets, full removal and replacement of the gravel base and asphalt pavement. The project also includes spot replacing driveway aprons, curb and gutter, sidewalk, improving pedestrian crossings, and installing traffic circles at the intersection of Starker Avenue and Woodvale Drive and Starker Avenue and Ellen Avenue.
Project Limits
Starker Avenue from Woodvale Drive to Droster Road
Project Schedule
Assessments to be Mailed: Feb. 23, 2024
Board of Public Works: March 6, 2024
Board of Public Works Approval: April 3, 2024
Common Council Approval: April 16, 2024
Bid Open Date: Fall 2024
Construction: April - August 2025
Public Involvement
There are a number of points of contact during this project where the public was encouraged to give feedback as part of public information meetings and public hearings. Dates, times and locations are indicated below:
Public Information Meetings
City Process, Meetings
Common Council: April 16, 2024
Board of Public Works: March 6, 2024
Mailings
Board of Public Works: March 6, 2024 Notice of Meeting Fact and Details Sheet Schedule of Assessments