Last Updated: 06/02/2022

Latest Update: June 02, 2022

In the NEWS:
June 01, 2022 City of Madison News Conference
News Conference: Dane Co. Executive Joe Parisi & Mayor Rhodes Conway Announce Clean Beach Corridor

June 01, 2022 Wisconsin State Journal
Open swim: Madison, Dane County partner on clean beach initiative

June 01, 2022 Channel 3000
Madison, Dane County announce new program aimed at keeping beaches algae-free

June 01, 2022 NBC15.com

Dane County and City of Madison aim to keep beaches from closing due to algae and E. coli

June 01, 2022 wortfm.org

Warner Park Gets Clean & Safe Beach Corridor

Project Overview

City Engineering will be replacing the existing beach house with a new park shelter and restrooms at Warner Beach.  The building will also include a pump room as part of the Clean Beach system announced in August 2019, a joint project between the City of Madison and Dane County.  Warner Beach Park Shelter will be the fifth prototype park shelter and restrooms.  Previous prototype shelters are located at Lake Edge Park; Esther Beach; Penn Park and Walter Street at Olbrich Park.

For more information on the Public Information meeting on this project, please visit Warner Park - Beach Shelter Replacement.

Follow the Progress on our FLICKR page!

Sept. 30, 2020: Construction on the Warner Beach Park Shelter officially started onsite the day after Labor Day, Sept. 8th. Asbestos abatement and demo was completed on the existing shelter to make way for the staking and excavation for the new shelter. As of this week, footings have been poured and forms are being set for the foundation walls. Follow our Flickr and EarthCam links to watch this building site take shape!

Project Schedule

City User Agency: Parks Division
Design and Planning: December - April 2020

Project Status: Construction!
1st Advertisement of Bid: June 12, 2020 available on Bid Express
Pre-Bid Building/Site Tour: Wednesday, June 24, 2020 @ 10:00 am at the project site, 1101 Woodward Dr.

Bid Due Date: July 09, 2020

Construction Start date: Sept. 8, 2020
Expected Completion date: June 05, 2021

"All information regarding dates/times/locations are informational and should be verified with official bidding documents posted on Bid Express."
 

Restroom/Shelter Rendering Updated March 11, 2020:

Warner Beach Park Shelter - TimberBark

In the News

Project History

August 4, 2020 File #61396

Awarding Public Works Contract No. 8850, Warner Beach Park Shelter

July 9, 2019 Public Meeting
Public meeting information and exhibits are available HERE