West Washington Avenue Resurfacing
Last Updated: 02/05/2021
Latest Update
2/5/2021 Update:
Thank you everyone who attended our virtual public information meeting last night. The recording is now ready for viewing.
Feb. 4, 2021 Public Information Meeting Recording
Feb. 4, 2021 Public Information Meeting PowerPoint Presentation
Project Overview
The purpose of this project is to resurface the street and replace utilities on West Washington Ave between Bedford Street and Broom Street. Proposed work includes removal and replacement of asphalt pavement, replacement of water main, sanitary sewer main and laterals, storm sewer and private storm sewer connections, installation of pedestrian street lighting, and replacement of curb and gutter, drive aprons, and sidewalk as needed. Crews will also install a protected intersection for pedestrians and bicyclists at the intersection of W Washington Avenue and Bassett Street. Crews will also install a parking protected bike lane on South Bassett Street between West Washington Avenue and West Main Street.
Project Limits
West Washington Avenue between Bedford Street and Broom Street
South Bassett Street between West Washington Avenue and West Main Street
Project Schedule
Design: Spring 2021
Construction: June 2021
Scheduled Completion: September 2021
Public Involvement
There are a number of points of contact during this project where the public is encouraged to give feedback as part of public information meetings and public hearings. Dates and times are indicated below:
Public Information Meetings
Feb. 4, 2021 Public Information Meeting Recording
Feb. 4, 2021 Public Information Meeting PowerPoint Presentation
City Meetings, Process
Anticipated schedule; dates are subject to change
Common Council: Information will be posted when available.
Board of Public Works: Information will be posted when available.