Starker Avenue Resurfacing with Utilities
June 18, 2025 Update
Construction along Starker Avenue continues throughout the project. The contractor is currently installing the sanitary sewer main and laterals between Woodvale Drive and Wendy Lane. At the same time, water main installation is underway from Woodvale Drive to Vondron Road, and storm sewer main installation is progressing throughout the entire project area.
All underground utility work is expected to be completed by early July.
In addition to utility work, the contractor has started cutting in and shaping the roadway at the intersection of Starker Avenue and Droster Road. As this underground work wraps up, crews will continue moving west along Starker Avenue to shape and prepare the rest of the street for concrete and asphalt pavement.
Once sections of the roadway are prepared, concrete work, including curb and gutter as well as driveway aprons will begin. This will start at Droster Road and continue westward.
The Contractor is in track to have the entire street cut in and shaped by the end of July.
The project remains on schedule for completion by the end of August 2025.
The Construction Inspector, Paul Lauby, 608-520-2378, plauby@cityofmadison.com will be the best on-site contact throughout construction.
View past project updates »Project Details
Project Information
Project Overview
The City is planning to resurface Starker Avenue from Woodvale Drive to Droster Road. The project includes replacing the sanitary sewer and laterals, water main, storm sewer main and inlets, full removal and replacement of the gravel base and asphalt pavement. The project also includes spot replacing driveway aprons, curb and gutter, sidewalk, improving pedestrian crossings, and installing traffic circles at the intersection of Starker Avenue and Woodvale Drive and Starker Avenue and Ellen Avenue.
Project Limits
Starker Avenue from Woodvale Drive to Droster Road
Project Schedule
Assessments to be Mailed: Feb. 23, 2024
Board of Public Works: March 6, 2024
Board of Public Works Approval: April 3, 2024
Common Council Approval: April 16, 2024
Bid Open Date: Fall 2024
Construction: April - August 2025
Public Involvement
There are a number of points of contact during this project where the public was encouraged to give feedback as part of public information meetings and public hearings. Dates, times and locations are indicated below:
Public Information Meetings
City Process, Meetings
Common Council: April 16, 2024
Board of Public Works: March 6, 2024
Mailings
Board of Public Works: March 6, 2024 Notice of Meeting Fact and Details Sheet Schedule of Assessments