Atticus Way
Archived Project
This project is complete. This information is available for reference purposes.July 8, 2025 Update
The construction of Rolling Way (connection of Atticus Way and Red Arrow Trail) is complete.
View past project updates »Project Details
Project Information
Overview

This project will connect Atticus Way and Red Arrow Trail with a new street. This will be a continuation of a private development project. The project will include removal of any existing pavement, new sidewalk on both sides of the proposed street, new asphalt pavement street, and new storm sewer infrastructure.
Project Limits
Atticus way to Red Arrow Trail
Project Schedule
Bid Advertisement: Spring 2024
Construction: Summer/Fall 2024
Public Involvement
Common Council: March 19, 2024
Board of Public Works: March 6, 2024
There are a number of points of contact during this project where the public is encouraged to give feedback as part of public information meetings and public hearings. Dates, times and locations are indicated below:
Public Information Meetings
A public information meeting has not been scheduled yet. It will be posted here once confirmed.
City Process, Meetings
Common Council March 19, 2024
Board of Public Works March 6, 2024
Mailings
Board of Public Works March 6, 2024 meeting notice, fact and detail sheet, assessment
Project Updates
July 8, 2025 Update
The construction of Rolling Way (connection of Atticus Way and Red Arrow Trail) is complete.
June 13, 2025 Update
MG&E has completed the removal and replacement of two poles, and overhead utilities have been relocated. The Contractor will continue with the grading, concrete work (sidewalk and curb & gutter), placement of gravel base, paving and terrace restoration.
April 4, 2025 Update
The Atticus Way construction project is scheduled to begin the week of April 14, 2025 and should be completed by late May 2025.
The City of Madison has awarded the contract to Speedway Sand & Gravel, Inc.
The City Inspector, Chris Horst, chorst@cityofmadison.com, 608-261-9972 will be the best on-site contact throughout construction work.
Please review the Atticus Way Construction Facts and Details document.
August 14, 2024 Update
The City awarded the Atticus Way project to Speedway Sand & Gravel Inc. Construction is anticipated to begin Spring 2025.
March 8, 2024 Update
The design team presented the project at the Board of Public Works on March 6, 2024. The Board approved the plans, specifications and assessments.
January 23, 2024 Update
This page has been created to provide information regarding the project and proposed improvements. On this page, you will find important information such as project scope, overview, limits and important dates. Regular updates will be posted on this page containing new information with the passing of each phase.