Public Health Madison Dane County South Clinic

October 26, 2026 Update

Quarter 4 Update
The Public Health Madison Dane County South Clinic Project is moving into Construction Document phase starting in early October 2026.  Bidding will be completed by the project's Construction Manager, JP Cullen, by late November 2026.  A Guaranteed Maximum Price (GMP) will be provided thereafter prior to proceeding with construction of the overall development starting in Quarter 1 2027.  Construction of the Public Health space will occur from June 2028 and June 2029, with Occupancy in July 2029.  The clinic would tentatively be open to the public in Quarter 4 2029.

View past project updates »

Project Details

Location

South Park Street & West Badger Rd.
Madison, WI 53713

Project Type

Status

In Design

Estimated Schedule

–

Alder District

  • District 14

Project Information

Project Overview

Madison’s Community Development Authority is redeveloping the block at S. Park Street and W. Badger Road. This area is approximately four acres of City-owned property. The development will include multifamily housing, a new fire station and a new public health clinic.  The public health facility will be approximately 30,000 – 35,000 square feet and be located on the first floor of a larger building. The estimated construction budget for the public health facility is $15M. Information about the overall project can be found on the Park Badger Redevelopment website. 

The City has selected a local team of professionals to engage the community, create a shared master plan, and embark on this redevelopment. The team was selected through a public, competitive proposal process. The main goal is to redevelop this block in a way that supports the community and keeps it affordable. To support this goal, the planning team held three community meetings.  Presentation materials from these meetings can be found on the City of Madison DPCED - Park Badger Redevelopment webpage.

Project Schedule

City User Agency: Public Health Madison Dane County (DHMDC)
A/E Consultant RFP Selection: Complete
Planning and Design: March 2025 - December 2026
Construction Start Date (Overall Development): Quarter 1 2027
Construction Start Date (Public Health Space): June 2028
Expected Completion Date (Public Health Space): Quarter 4 2029

Public Involvement

There are a number of points of contact during this project where the public is encouraged to give feedback as part of public information meetings and public hearings. Dates, times and locations will be indicated below when scheduled.

Project Updates

October 26, 2026 Update

Quarter 4 Update
The Public Health Madison Dane County South Clinic Project is moving into Construction Document phase starting in early October 2026.  Bidding will be completed by the project's Construction Manager, JP Cullen, by late November 2026.  A Guaranteed Maximum Price (GMP) will be provided thereafter prior to proceeding with construction of the overall development starting in Quarter 1 2027.  Construction of the Public Health space will occur from June 2028 and June 2029, with Occupancy in July 2029.  The clinic would tentatively be open to the public in Quarter 4 2029.

July 3, 2026 Update

Quarter 3 2026 Update
Potter Lawson and sub-consultants have been working with Engineering staff and Public Health Madison Dane County staff to work through the design of the interior spaces of the new health clinic.  Each department in the clinic has been having focus meetings to provide critical feedback on the plans.  Potter Lawson Architects will continue to coordinate clinic needs with the larger development design team so things like windows, doors, and site amenities are located properly and integrated for a cohesive design.   The clinic design is currently in the design development phase.
 