Buffalo Trail, Barron Court, Green Lake Pass
April 18, 2025 Update
The Board of Public Works (BPW) approved the plans, specifications, and schedule of assessments for Buffalo Trail, Barron Court, and Green Lake Pass on 4/16/25. The project team also presented and received approval from the BPW for the proposed 30 ft street widths. The project will be on the Common Council agenda on Tuesday, May 6, 2025.
Next steps include finalizing the design, plans, and specifications in preparation for advertising the project for contractor bids in late May 2025.
View past project updates »Project Details
Project Information
Project Overview
The City is planning construction on Buffalo Trail, Barron Court, and Green Lake Pass The project includes full removal and replacement of the asphalt pavement, gravel base, driveway ramps, curb and gutter, installation of new storm sewer, and spot replacement of sidewalk. Sanitary main and laterals will be replaced on Buffalo Trail between Door Drive and N Eau Claire Ave.
Project Limits
Buffalo Trail – Green Lake Pass to N Eau Claire Avenue
Barron Court – South end to Buffalo Trail
Green Lake Pass – Door Drive to Buffalo Trail
Project Schedule
Design: Winter/Spring 2025
Bids Advertised: Summer 2025
Construction: Fall 2025
Public Involvement
There are a number of points of contact during this project where the public is encouraged to give feedback as part of public information meetings and public hearings. Dates, times and locations are indicated below:
Public Information Meetings
March 20, 2025 Public Information Meeting Recording
March 20, 2025 Public Information Meeting PowerPoint Presentation
Mailings
Board of Public Works: April 16, 2025 Notice of Meeting Fact and Details Sheet Schedule of Assessments
Questionnaire
Please complete the project questionnaire by 3 p.m., March 27, 2025.
Buffalo Trail, Barron Court, Green Lake Pass Questionnaire
City Process, Meetings
Common Council May 6, 2025
Board of Public Works April 16, 2025