Regent Street Reconstruction
September 16, 2025 Update
Thank you to everyone who attended the Sept. 15, 2025 Public Information Meeting. The meeting materials are now available:
Sept. 15, 2025 Public Information Meeting Recording
Sept. 15, 2025 Public Information Meeting PowerPoint Presentation
Questionnaire
Please complete the project questionnaire by Sept. 22, 2025:
Regent Street Reconstruction Questionnaire
Project Details
Project Information
Project Overview
The City is planning to reconstruct Regent Street (Randall Avenue to S. Park Street).
The project includes the replacement of a large box culvert, sanitary sewer and laterals, water main and reconnection of water services, storm sewer structures and laterals, street lighting, traffic signals, curb and gutter, sidewalk, driveway aprons, gravel base, pavement, pavement marking, and signing. The water main replacement will extend beyond Randall Street toward Monroe Street. Madison Gas & Electric is planning to replace the gas main during the project. AT&T as well as Charter Communications and other communication companies may also replace facilities during the project.
Project Limits
Randall Avenue to S. Park Street
Project Schedule
Preliminary Design: Spring/Fall/Winter 2025/2026
Final Design: Winter/Spring/Summer/Fall 2026
Bids Advertised: Fall 2026
Construction: Spring – Fall 2027
Public Involvement
There are a number of points of contact during this project where the public is encouraged to give feedback as part of public information meetings and public hearings. Dates, times and locations are indicated below:
Public Information Meetings
Sept. 15, 2025 Public Information Meeting Recording
Sept. 15, 2025 Public Information Meeting PowerPoint Presentation
Questionnaire
Please complete the project questionnaire by Sept. 22, 2025:
Regent Street Reconstruction Questionnaire
City Process, Meetings
Common Council Information will be posted when available
Board of Public Works Information will be posted when available