Financial Summary & Fiscal Constraint Information

The tables below show the total funding needed to implement the transportation improvements included in this five-year Transportation Improvement Program (TIP).

Programmed expenditures account for annual inflation rates ranging from 2.79% to 3.20%, as requested by the Wisconsin Department of Transportation (WisDOT). These rates were applied to all projects except local projects submitted with inflation already included. The inflation rates are also reflected in the individual project listings.

Transportation Funding by Geographic Area (2027–2031)

The tables below summarize funding programmed for transportation projects and programs across Dane County from 2027–2031. Funding is shown in year-of-expenditure dollars, with 2031 included for informational purposes only.

Funding is broken down by local, state, and federal sources for projects within the Madison Metropolitan Planning Area and the outer areas of Dane County.

Madison Metropolitan Planning Area

Explore funding by source for projects within the metropolitan planning area.

Local Funding

Funding Source20272028202920302031Total
City of Fitchburg$8,234,158$4,475,323$11,418,876$5,029,867$7,038,282$35,836,506
City of Madison$95,136,357$48,188,047$50,990,744$50,481,521$50,341,990$295,138,659
City of Middleton$1,420,000$0$2,000,000$63,269$0$3,483,269
City of Monona$976,588$2,855,838$170,721$1,375,860$2,981,488$8,360,495
City of Stoughton$1,514,235$1,366,484$3,142,020$2,498,843$531,366$9,052,948
City of Sun Prairie$6,808,326$10,096,755$6,554,223$5,120,094$962,271$29,541,669
City of Verona$3,979,000$2,309,000$1,075,000$1,199,903$75,000$8,637,903
Dane County$14,261,857$10,936,870$20,151,120$3,282,870$5,850,870$54,483,587
Greater Madison MPO$28,517$29,658$30,844$32,078$33,361$154,458
Madison & Other$32,779,000$33,434,000$34,103,000$34,785,000$35,481,000$170,582,000
Other$459,225$845,137$172,761$58,332$0$1,535,455
Village of Cottage Grove$0$1,245,000$1,710,000$725,000$0$3,680,000
Village of DeForest$1,095,714$15,670,658$1,824,232$0$0$18,590,604
Village of McFarland$2,798,080$5,827,700$4,291,900$0$730,800$13,648,480
Village of Mount Horeb$1,565,185$0$0$0$0$1,565,185
Village of Oregon$5,945,000$6,356,000$243,000$5,870,000$5,012,000$23,426,000
Village of Waunakee$1,338,000$0$1,950,000$0$0$3,288,000
Wisconsin & Southern Railroad$10,200$0$0$0$0$10,200
Local Subtotal$178,349,442$143,636,470$139,828,441$110,522,637$109,038,428$681,015,418

State Funding

Funding Source20272028202920302031Total
85.20 (Transit)$20,978,252$21,417,045$21,858,976$22,316,544$22,785,593$109,356,410
85.21 (Transit)$656,660$656,660$656,660$656,660$656,600$3,283,240
Local Road Improvement Program$1,146,043$414,250$0$0$0$1,560,293
Wisconsin Department of Transportation$84,142,256$10,971,435$10,152,525$39,927,688$34,376,849$179,570,753
Wisconsin DNR Recreational Trail Program$99,500$0$0$0$0$99,500
State Subtotal$107,022,711$33,459,390$32,668,161$62,900,892$57,819,042$293,870,196

Federal Funding

Funding Source20272028202920302031Total
Section 5307$17,858,000$14,583,000$14,737,000$1,022,000$1,036,000$49,236,000
Section 5309$118,132,000$0$0$0$0$118,132,000
Section 5311$2,130,335$2,130,335$2,130,335$2,130,335$2,130,335$10,651,675
Section 5337$2,555,000$2,690,000$2,725,000$2,762,000$2,800,000$13,532,000
Section 5339$1,930,000$1,930,000$1,930,000$1,930,000$1,930,000$9,650,000
Advanced Transportation Technology and Innovation (ATTAIN)$1,295,289$2,697,445$387,254$0$0$4,379,988
Bridge Replacement and Rehabilitation$1,724,519$0$0$0$0$1,724,519
Carbon Reduction Program (CRP)$0$3,017,176$0$0$0$3,017,176
Earmark$850,000$0$0$0$0$850,000
Highway Safety Improvement Program (HSIP) – Rail Highway Protective Devices$1,603,000$236,507$0$0$0$1,839,507
Highway Safety Improvement Program (HSIP)$1,917,125$0$397,923$975,000$2,524,823$5,814,871
National Highway Performance Program$45,262,972$14,586,627$39,446,747$110,010,752$89,391,480$298,698,578
Surface Transportation Block Grant Program – Madison Urban Area Sub-allocation$11,313,074$12,234,301$9,143,212$8,973,229$10,840,465$52,504,281
Surface Transportation Block Grant Program – State Flexibility$9,730,638$7,468,649$6,541,931$48,480,000$46,674,810$118,896,028
Surface Transportation Block Grant Program – Transportation Alternatives Set-Aside$3,617,000$1,271,000$1,230,340$1,664,456$0$7,782,796
Federal Subtotal$219,918,952$62,845,040$78,669,742$177,947,772$157,327,913$696,709,419

Total Planning Area Funding (All Sources)

YearTotal Funding
2027$505,291,105
2028$239,940,900
2029$251,166,344
2030$351,371,301
2031$324,185,383
2027–2031 Total$1,671,595,033

Outer Areas of Dane County

Explore funding for projects outside the metropolitan planning area.

Local Funding

Funding Source2027202820292030Total
Dane County$5,435,000$2,600,000$2,135,000$5,500,000$15,670,000
Village of Mazomanie—$150,000——$150,000
Local Subtotal$5,435,000$2,750,000$2,135,000$5,500,000$15,820,000

State Funding

Funding Source2027202820292030Total
Local Road Improvement Program$479,000——$800,000$1,279,000
Wisconsin Department of Transportation—$554,185——$554,185
State Subtotal$479,000$554,185—$800,000$1,833,185

Federal Funding

Funding Source2027202820292030Total
Bridge Replacement and Rehabilitation—$1,180,000——$1,180,000
Surface Transportation Block Grant Program – Small Urban/Rural Area——$2,534,000—$2,534,000
Surface Transportation Block Grant Program – State Flexibility—$2,216,742——$2,216,742
Federal Subtotal—$3,396,742$2,534,000—$5,930,742

Total Outer Area Funding (All Sources)

YearTotal Funding
2027$5,914,000
2028$6,700,927
2029$4,669,000
2030$6,300,000
2027–2030 Total$23,583,927

Additional Funding Notes

  • Transit Funding: Funding estimates are based on anticipated needs and future funding levels. See Metro Transit System Projected Expenses and Revenues for more details.
  • Projects Spanning Both Areas: Some projects, like Interstate 39/90/94, cross both the Metropolitan Planning Area and Outer Area. Their full costs are included in the Metropolitan Planning Area because they couldn't be separated.
  • City of Madison Funding: Includes parking costs funded through user fees, as well as the City's share of federal transit capital grants.

Federal Transportation Funding: Programmed vs. Available (2027–2031)

The tables below compare programmed transportation expenditures with estimated available federal funding from the Federal Highway Administration (FHWA) and Federal Transit Administration (FTA) within the Madison Metropolitan Planning Area. All amounts are expressed in year-of-expenditure dollars.

The comparison covers the 2027–2030 Transportation Improvement Program (TIP), with 2031 included for informational purposes only.

The Interstate 39/90/94 Capacity Expansion project from Hanson Road to the North County Line (NCL) is excluded from this analysis because fiscal constraint for this project is addressed at the state level.

Federal Highway Administration (FHWA) Funding

Funding ProgramProgrammed 2027Programmed 2028Programmed 2029Programmed 2030Programmed 2031Available 2027Available 2028Available 2029Available 2030Available 2031
ATTAIN$1,295,289$2,697,445$387,254$0$0$1,295,289$2,697,445$387,254$0$0
Bridge Replacement and Rehabilitation$1,724,519$1,180,000$0$0$0$1,724,519$1,180,000—$0$0
Carbon Reduction Program$0$3,017,176$0$0$0—$3,017,176—$0$0
HSIP – Rail Highway Protective Devices$1,603,000$236,507$0$0$0$1,603,000$236,507—$0$0
HSIP Highway Safety Improvement Program$1,917,125$0$397,923$975,000$2,524,823$1,917,125—$397,923$975,000$2,524,823
National Highway Performance Program$45,262,972$14,586,627$39,446,747$36,090,531$89,391,480$45,262,972$14,586,627$39,446,747$36,090,531$89,391,480
Surface Transportation Block Grant Program – Madison Urban Area Sub-allocation$11,313,074$12,234,301$9,143,212$8,973,229$10,840,465$11,428,625$10,848,800$10,232,282$10,516,354$12,065,659
Surface Transportation Block Grant Program – Small Urban/Rural Area$0$0$2,534,000$0$0——$2,534,000$0$0
Surface Transportation Block Grant Program – State Flexibility$9,730,638$9,685,391$6,541,931$48,480,000$46,674,810$9,730,638$9,685,391$6,541,931$48,480,000$46,674,810
Surface Transportation Block Grant Program – Transportation Alternatives Set Aside$3,617,000$1,271,000$1,230,340$1,664,456$0$3,312,495$1,158,539$1,351,358$1,584,041$0

Federal Transit Administration (FTA) Funding

Funding ProgramProgrammed 2027Programmed 2028Programmed 2029Programmed 2030Programmed 2031Available 2027Available 2028Available 2029Available 2030Available 2031
5307$17,858,000$14,583,000$14,737,000$1,022,000$1,036,000$17,858,000$14,583,000$14,737,000$1,022,000$1,036,000
5309$118,132,000$0$0$0$0$118,132,000——$0$0
5311$2,130,335$2,130,335$2,130,335$2,130,335$2,130,335$2,130,335$2,130,335$2,130,335$2,130,335$2,130,335
5337$2,555,000$2,690,000$2,725,000$2,762,000$2,800,000$2,555,000$2,690,000$2,725,000$2,762,000$2,800,000
5339$1,930,000$1,930,000$1,930,000$1,930,000$1,930,000$1,930,000$1,930,000$1,930,000$1,930,000$1,930,000

Notes and Methodology

  • Fiscal-year conventions: Programmed expenditures and estimated available funding are generally reported by calendar year. However, estimated available funding for the Surface Transportation Block Grant Program (STBG) Madison Urban Area sub-allocation and the Transportation Alternatives Program (TAP) Set-Aside Program is reported by federal fiscal year.
  • Transit funding: Transit funding has not yet been fully programmed and is based on identified needs and anticipated future funding levels. See the Madison Metro Transit System — Projected Expenses and Revenues tables for additional information.

Fiscal-Constraint Assessment

The four-year totals indicate that estimated funding is reasonably expected to be available to cover programmed expenditures for the 2027–2030 TIP.

In some years, programmed expenditures may appear to exceed estimated available funding. This can occur for several reasons:

  • Previously programmed projects: Projects selected in an earlier TIP may remain listed even if they do not require additional funding, such as certain transit capital projects.
  • Large transportation projects: Projects such as freeway reconstruction may be programmed by WisDOT over multiple years and authorized using FHWA Advance Construction allowances or funded through alternative sources not reflected in this fiscal-constraint analysis.
  • Differences in fiscal years: The TIP uses calendar years, while the State fiscal year runs from July 1 through June 30. Depending on when federal funding becomes available, expenditures scheduled for a particular calendar year may appear to exceed estimated available funding.

These factors help explain differences between programmed expenditures and estimated available funding in individual years while maintaining fiscal constraint across the four-year TIP period.

Projected Transportation Expenses and Revenues (2027–2031)

The tables below summarize projected expenses and revenues for transportation projects in the Madison Metropolitan Area, expressed in year-of-expenditure dollars.

Projected Expenses

State & Federal

Expense Category202720282029203020312027–2031 Total
State Highway Operations and Maintenance$10,917$11,237$11,551$11,899$12,279$57,884
Federal Construction (NHPP, STBG FLEX, HSIP) Funding$58,514$22,292$46,387$58,139$138,591$323,922
State Construction Funding$84,142$10,971$10,153$39,928$34,377$179,571
Subtotal$153,573$44,501$68,090$109,965$185,247$561,377

Dane County & Communities

Expense Category202720282029203020312027–2031 Total
Street Operations and Maintenance$70,938$73,016$75,054$77,313$79,787$376,107
Street Construction$76,427$78,667$80,862$83,295$85,961$405,212
Street-Related Facilities$14,637$15,065$15,486$15,952$16,462$77,602
Subtotal$162,002$166,748$171,401$176,560$182,210$858,921

Metro Transit

Expense Category202720282029203020312027–2031 Total
Capital Expenses$10,074$11,116$11,454$11,801$12,166$56,610
Operating Expenses$92,175$95,429$98,806$102,309$105,584$494,303
Subtotal$102,249$106,545$110,259$114,110$117,750$550,913

Total Projected Expenses

202720282029203020312027–2031 Total
$417,824$317,794$349,750$400,635$485,208$1,971,211

Projected Revenues

State & Federal

Revenue Category202720282029203020312027–2031 Total
State Highway Operations and Maintenance$10,917$11,237$11,551$11,899$12,279$57,884
Federal Construction (NHPP, STBG FLEX, HSIP) Funding$58,514$22,292$46,387$58,139$138,591$323,922
State Construction Funding$84,142$10,971$10,153$39,928$34,377$179,571
Subtotal$153,573$44,501$68,090$109,965$185,247$561,377

Dane County & Communities

Revenue Category202720282029203020312027–2031 Total
Street Operations and Maintenance$70,938$73,016$75,054$77,313$79,787$376,107
Street Construction$76,427$78,667$80,862$83,295$85,961$405,212
Street-Related Facilities$14,637$15,065$15,486$15,952$16,462$77,602
Subtotal$162,002$166,748$171,401$176,560$182,210$858,921

Metro Transit

Revenue Category202720282029203020312027–2031 Total
Capital Revenues$10,074$11,116$11,454$11,801$12,166$56,610
Operating Revenues$92,175$95,429$98,806$102,309$105,584$494,303
Subtotal$102,249$106,545$110,259$114,110$117,750$550,913

Total Projected Revenues

202720282029203020312027–2031 Total
$417,824$317,794$349,750$400,635$485,208$1,971,211

Metro Transit Financial Capacity Summary

The tables below summarize Metro Transit's fixed-route ridership, revenue service, operating expenses, and passenger revenue. They also present projected expenses and revenues for the Metro Transit system from 2026–2031, expressed in year-of-expenditure dollars.

Metro Transit Fixed-Route System: Revenue Service Statistics

Source: Metro Transit National Transit Database (NTD) Reports.

Revenue Service Statistics (2006–2024)

YearTotal PassengersRevenue Vehicle HoursPassengers/Revenue Vehicle HourPassenger RevenueRevenue/PassengerOperating ExpensesExpense/PassengerRevenue as % Expense
20249,176,868434,50321.1$8,507,697$0.93$62,852,017$6.8513.5%
20239,403,885379,14224.8$9,345,849$0.99$57,399,114$6.1016.3%
20228,287,021345,89924.0$8,384,512$1.01$51,022,930$6.1616.4%
20215,390,018333,24516.2$8,329,002$1.55$50,061,816$9.2916.6%
20204,693,426309,44615.2$7,725,570$1.65$49,175,986$10.4815.7%
201912,856,514403,57031.9$12,403,091$0.96$49,447,862$3.8525.1%
201813,230,698406,41032.6$12,630,370$0.95$48,018,558$3.6326.3%
201712,817,077404,39531.7$12,847,443$1.00$47,343,970$3.6927.1%
201613,305,291403,82532.9$12,799,840$0.96$46,920,051$3.5327.3%
201514,358,261405,80235.4$12,953,527$0.90$46,116,510$3.2128.1%
201415,223,961403,46637.7$13,012,124$0.85$44,909,155$2.9529.0%
201314,740,736391,10037.7$12,596,966$0.85$43,031,329$2.9229.3%
201214,592,214382,45438.2$11,970,811$0.82$41,522,887$2.8528.8%
201114,923,970383,10739.0$11,712,963$0.78$42,090,315$2.8227.8%
201013,623,461381,76835.7$10,737,634$0.79$40,434,049$2.9726.6%
200913,588,426372,13436.5$9,992,237$0.74$40,547,797$2.9824.6%
200813,433,139366,78636.6$9,083,451$0.68$41,288,025$3.0722.0%
200712,672,334367,13034.5$8,721,876$0.69$36,199,459$2.8624.1%
200612,034,468365,54732.9$7,912,169$0.66$35,143,898$2.9222.5%

Revenue Service Statistics (1985–2005)

YearTotal PassengersRevenue Vehicle HoursPassengers per Revenue Vehicle HourPassenger RevenueRevenue per PassengerOperating ExpensesExpense per PassengerRevenue as % Expense
200511,475,597364,49131.5$7,361,203$0.64$32,974,246$2.8722.3%
200410,962,345365,82630.0$6,295,638$0.57$31,732,151$2.8919.8%
200310,934,125356,13730.7$5,910,084$0.54$30,283,752$2.7719.5%
200210,895,089363,06330.0$6,172,079$0.57$30,029,568$2.7620.6%
200110,210,834373,33127.4$6,308,430$0.62$28,637,012$2.8022.0%
200010,065,495385,07226.1$5,821,511$0.58$28,232,128$2.8020.6%
199910,110,441393,88325.7$5,621,793$0.56$27,576,045$2.7320.4%
199810,097,867344,20429.3$5,862,692$0.58$25,548,528$2.5322.9%
199710,370,107315,39532.9$6,104,538$0.59$23,054,329$2.2226.5%
19969,816,095321,77830.5$5,914,372$0.60$22,355,149$2.2826.5%
19959,600,678318,24830.2$5,271,921$0.55$20,666,830$2.1525.5%
19949,655,615311,88431.0$5,422,093$0.56$19,962,607$2.0727.2%
19939,554,959309,89530.8$5,365,315$0.56$20,326,803$2.1326.4%
19929,560,739309,99230.8$5,078,327$0.53$19,147,083$2.0026.5%
19919,389,637295,04931.8$4,937,700$0.53$18,165,516$1.9327.2%
19909,096,485293,99530.9$4,663,216$0.51$16,498,683$1.8128.3%
19899,047,940287,48631.5$4,598,717$0.51$15,424,513$1.7029.8%
19889,540,787308,77730.9$4,734,182$0.50$15,249,227$1.6031.0%
198710,063,120332,13730.3$4,988,896$0.50$14,751,192$1.4733.8%
198611,301,361314,79535.9$4,965,555$0.44$14,178,969$1.2535.0%
198511,946,337325,31436.7$5,172,913$0.43$13,922,792$1.1737.2%

Notes

  1. Total Passengers: Includes all passenger boardings (unlinked trips), including those using cash fares, 10-ride cards, unlimited-ride passes, or transfers. It also includes free rides on campus circulators and rides by children age five and younger. Because of unlimited-ride passes, tracking linked trips is difficult. A 2024 on-board passenger survey found that approximately 20% of trips include a transfer.
  2. Revenue Vehicle Hours: Includes time when buses are available to passengers on routes, including recovery and layover time. Excludes deadhead travel, such as trips between the garage and a route or between routes.
  3. Inflation: Dollar amounts are not adjusted for inflation.
  4. Operating Expenses: Excludes depreciation, interest expenses, and capital leases and rentals.

Madison Metro Transit System — Projected Expenses and Revenues

The 2026 expenses and revenues are based on the City Executive Budget. All figures are preliminary estimates and are subject to final state and federal budget authorizations. 

Differences between these projections and the Transportation Improvement Program (TIP) project listings reflect the City's practice of budgeting Federal Transit Administration (FTA) funding in the prior year's Capital Improvement Plan (CIP).

Projected Expenses

Category2026 Budgeted2027 Projected2028 Projected2029 Projected2030 Projected2031 Projected
Capital Costs$14,935,000$10,074,236$11,115,931$11,453,509$11,800,614$12,166,033
Operating Costs$87,255,551$92,174,580$95,429,047$98,805,687$102,309,161$105,584,398
Total Costs$102,190,551$102,248,816$106,544,978$110,259,196$114,109,774$117,750,431

Capital costs include fixed-asset and operating costs projected to be funded through FTA Sections 5307, 5337, and 5339, as well as other discretionary grants. These costs also include the Bus Rapid Transit (BRT) project.

Operating costs are reported net of expenses funded by FTA Section 5307 grants. They include debt principal and interest but exclude depreciation.

Projected Revenues

Category2026 Budgeted2027 Projected2028 Projected2029 Projected2030 Projected2031 Projected
FTA Sections 5307, 5337, and 5339 Capital$23,566,731$16,706,741$16,326,148$15,971,638$16,305,810$16,648,559
State Section 85.20$18,343,703$18,400,000$18,400,000$18,400,000$18,400,000$18,400,000
Farebox and Other Revenue$19,259,980$22,289,000$20,344,000$20,674,140$21,010,135$21,352,096
Local Funds — Madison$28,220,445$30,573,076$36,194,830$39,475,018$42,183,277$44,652,908
Other Local Funds$12,799,692$14,280,000$15,280,000$15,738,400$16,210,552$16,696,869
Total Revenues$102,190,551$102,248,816$106,544,978$110,259,196$114,109,774$117,750,431

Notes

  1. Section 5307 Funding: Eligible operating expenses include preventive maintenance, tire leasing, planning, and related activities.
  2. Sections 5337 and 5339 Funding: FTA Section 5337 (State of Good Repair) and Section 5339 (Bus and Bus Facilities) are formula funding programs established under the Infrastructure Investment and Jobs Act (IIJA), also known as the Bipartisan Infrastructure Law (BIL). Projected funding levels are based on authorized funding.
  3. State Section 85.20 Funding: Funding is assumed to remain constant throughout the projection period, with no annual increases.
  4. Capital Financing: General obligation (G.O.) debt is used to finance major capital expenses. Smaller capital expenses are assumed to be funded through current-year taxes and are included under “Local Funds — Madison."

Surface Transportation Block Grant (STBG) Urban Funds

The Surface Transportation Block Grant (STBG) Urban program, formerly known as the Surface Transportation Program (STP) Urban, provides federal funding for a wide range of transportation improvements in the Madison Urban Area.

Originally established under the Intermodal Surface Transportation Efficiency Act (ISTEA), the program has continued through subsequent federal transportation legislation, including TEA-21, SAFETEA-LU, MAP-21, the FAST Act, and the Infrastructure Investment and Jobs Act (IIJA), also known as the Bipartisan Infrastructure Law (BIL).

Along with Federal Transit Administration (FTA) Section 5307 formula funding allocated annually to Metro Transit, STBG Urban funding is a primary source of federal support for local transportation improvements in the Madison Urban Area. A summary of STBG Urban funds programmed for 2027–2031 is provided in the funding tables above.

Project Selection and Funding

Local governments and Dane County are invited to submit STBG Urban project proposals every two years as part of the Transportation Improvement Program (TIP) development process.

MPO staff evaluate, score, and rank submitted projects, then review the evaluations with the Technical Coordinating Committee before the MPO Policy Board makes final funding decisions.

Requests for STBG Urban funding typically exceed the amount available. To distribute limited funding across more projects, the MPO Policy Board has adjusted its cost-sharing policy over time:

  • 2010: Changed the federal/local cost share from 80/20 to 50/50 for major STP Urban projects.
  • 2015: Increased the federal share to 60%, with a 40% local match, beginning with newly programmed projects for 2019–2020.
  • 2023: Increased the federal share to 65%, with a 35% local match, beginning with newly programmed projects for the 2025–2029 program cycle.