Public Comment Summary: Draft 2027–2031 TIP

The Draft 2027–2031 Transportation Improvement Program (TIP) was published in August 2026 and posted on the MPO's website.

A notice of its availability and a summary were distributed to Dane County communities, the MPO's advisory committees, WisDOT, Metro Transit, and other agency staff. An email notice was also sent to Dane County Board members, local transportation and public works committees, and other interested organizations and individuals.

Private transportation providers in the county received a notice and a copy of the draft transit projects.


The draft TIP was reviewed through the following meetings:

  • Preliminary Review No. 1: Technical Coordinating Committee in July and MPO Policy Board in August.
  • Review No. 2: MPO Policy Board and Technical Coordinating Committee in September, including a public hearing on September 2.

Meeting agendas were posted on the MPO's website.

Public Hearing

The public hearing was held virtually during the MPO Policy Board meeting on September 2, 2026. No members of the public registered to speak. Staff presented comments that a Madison resident submitted by email.

Technical Coordinating Committee (TCC) Meetings

July 22, 2026

Staff reviewed proposed STBG-Urban funding increases for the Glacial Drumlin Trail and Vinburn Road projects.

Staff also provided an update on the development of the 2027–2031 TIP using the new eTIP software. Local community staff were entering transportation project information into the platform, with MPO staff reviewing the information and providing assistance as needed.

Bruun asked MPO staff to send a reminder email close to the deadline for finalizing TIP project submittals. He noted that the deadline falls near the time Monona will be finalizing its budget, which could result in project changes.

September 23, 2026

The director of Humane-Dane spoke about the importance of creating livable, walkable communities that support local businesses and locally produced food. He emphasized the importance of rail transit and developing communities in ways that make it easier for people to live without a car.

Draft TIP Update

Staff reviewed the public participation activities used to gather input on the draft TIP. They also explained the transition from a PDF document to a website, making the TIP accessible to people with disabilities, including those using screen readers, and compliant with web content accessibility guidelines.

Staff summarized two changes to the draft TIP:

  • Addition of the Old Middleton Road Underpass and Path project in Madison.
  • Revision of the Troy Drive Railroad Bridge project to show that construction funding occurred in 2023 rather than 2025.

Staff also outlined a proposed TIP amendment schedule intended to make the process more efficient and limit amendments to no more than every other month. They reviewed several major projects included in the TIP.

Committee Recommendation

Acton moved, Hall seconded, to recommend approval of the Draft 2027–2031 Transportation Improvement Program for the Madison Metropolitan Area and Dane County, as presented. Motion carried.

MPO Policy Board Review & Adoption

August 5, 2026

Funding Programs

At the August meeting, staff summarized the STBG-U, TAP, and CRP programs and reviewed proposed STBG-Urban funding increases for the Glacial Drumlin Trail and Vinburn Road projects.

Callin asked how Carbon Reduction Program funding is apportioned to the MPO. Staff explained that the program is not expected to continue and that no formal funding amount has been established for future years.

New eTIP Platform and Review Schedule

Staff demonstrated how to navigate the new eTIP website. Kanning and Lyman had led several training sessions with local municipal staff on entering project listings into the platform.

Staff outlined the planned review and adoption schedule:

  • August 19: Release the draft TIP.
  • September 2: Hold a public hearing at the Policy Board meeting.
  • September 23: Provide the Technical Coordinating Committee an opportunity to make recommendations.
  • October 7: Provide the Policy Board an opportunity to adopt the TIP.

Board Questions and Feedback

Mayor Janairo and Alder Lieberman suggested improvements to the interactive eTIP map's color scheme and usability. Staff said they would work with the EcoInteractive team to address those suggestions.

Howe asked whether the costs shown in the table were in current year or year of expenditure dollars. Staff clarified that the amounts were shown in year of expenditure dollars. Howe also asked whether project listings would include total improvement costs, and Kanning confirmed that they would.

October 7, 2026

Staff presented the addition/change sheet listing proposed changes to the draft TIP. They noted that the TCC had reviewed the changes at its September meeting and recommended approval of the TIP with those changes.

Kvalo moved, Barushok seconded, to adopt the 2027–2031 TIP with the changes reflected in the Addition/Change sheet. Motion carried.

Public Involvement Timeline

The following timeline outlines public involvement, project coordination, and review for the 2027–2031 Transportation Improvement Program (TIP) for the Madison Metropolitan Area and Dane County.

  1. Notice and Request for Projects Completed

    Notify local units of government and the public, and request proposed project listings.

  2. Project Submittal Deadline Completed

    Project listings and applications are due to the MPO.

  3. Project Coordination and Review Completed

    Coordinate among agencies to address discrepancies in multi-jurisdictional projects or projects with federal or state funding. The MPO and Technical Coordinating Committee (TCC) review all projects in the TIP.

  4. Draft TIP Availability Notice Completed

    Send an email notice announcing the availability of the draft TIP, including the draft listing of all projects.

  5. Public Hearing Completed

    The MPO formally receives testimony and comments on the draft TIP at a public hearing.

  6. TCC Recommendation Completed

    The TCC provides final comments and a recommendation to the MPO.

  7. Final MPO Action Completed

    The MPO takes final action on the TIP.

  8. Submittal to WisDOT Upcoming

    Submit the complete final TIP report and appendices to WisDOT for approval.


Note: The Greater Madison MPO accepts applications for STBG-Urban projects every other year, in odd-numbered years, in conjunction with the state biennial budget and WisDOT local program cycle.

Public Comments Received 

By Email

Intersection Improvements (S. Whitney Way and Odana Road)

Public Comment

The issue here is that the project description makes no mention of including bike lanes in this intersection redesign. According to Madison's Complete Green Streets ordinance, both of the streets passing through this intersection are supposed to have bike lanes. But currently, they don't. 

For example, Odana Rd has bike lanes to the east and west of this intersection, but the bike lanes are just missing from the stretch of Odana Rd that passes through the intersection. Therefore, any redesign of this intersection needs to include addressing these gaps or at least take into account that, in the future, these streets will have bike lanes, even if that means eliminating redundant travel lanes.

Response

This project is a safety improvement project that was awarded funds to improve safety and reduce vehicle crashes. It is not a complete reconstruction. The funds are awarded to address distinct issues.

The project addresses safety in the following ways: improving signal visibility by adding signal heads over each traffic lane and high visibility backplates, improving pedestrian facilities by widening medians, installing high visibility crosswalks and accessible pedestrian signals, and reducing driver confusion by eliminating the extra northbound receiving lane.

A complete reconstruction would be a different class of project with extensive utility work as well as significant right of way acquisition. That would likely be included with a full Whitney Way reconstruct or Odana reconstruct in the future.

Mineral Point Road Pavement Replacement (Beltline Highway to S. High Point Road)

Public Comment

The description mentions adding a path on the north side of the street, where there is already a path. But approved designs for this project actually included a portion of a path on the south side of the street to bring cyclists up to sidewalk level in the 7900 block, where the bike lane currently disappears unexpectedly.

Response

This is correct. The approved design includes a portion of path on the south side of Mineral Point Road.

Regent Street Reconstruction (Randall Avenue to Park Street)

Public Comment

Current designs for Regent Street do not include any bike facility, so as to create unneeded parking. This is in violation of Madison's Complete Green Streets ordinance and Dane County's climate goals of reducing Vehicle Miles Traveled (VMT).

Therefore, I would recommend not approving this project in its current form.

Response

The City of Madison Transportation Commission and Common Council discussed this issue extensively. The project does not violate the ordinance. 

The Transportation Commission has the authority to approve variances when street designs need to differ from the parameters identified in the Guide to address a specific issue. Both the Transportation Commission and Common Council approved this design.

Pleasant View Road Reconstruction and Capacity Expansion (Mineral Point Road to Timber Wolf Trail)

Public Comment

A multi-use path is much needed here! However, WisDOT data from 2025 shows only about 10k vehicle trips per day, so two lanes each way would be excessive. Rebuilding this as one lane each way would be better for safety, and at a lower cost.

Response

The street cross section will be determined during the design phase. The design must follow the state Facilities Development Manual, which requires the cross section to accommodate both existing traffic and projected traffic conditions 20 years into the future. 

Substantial growth is expected in this area of the city.

Hoepker Road and Portage Road Reconstruction (Hoepker Road: I-39/90/94 to Portage Road; Portage Road: Hoepker Road to Hanson Road)

Public Comment

The project description ought to include a bike/ped facility. Portage Rd is a crucial connection for municipalities to the north; Hoepker Rd is one of the few low-stress crossings of I-90 and will soon connect to a multi-use path along north Stoughton Rd.

Response

This project is expected to include protected bicycle facilities.

Interstate 39/90/94 Reconstruction and Expansion (South Beltline/USH 12/18 to Hanson Road)

Public Comment

I urge you to take this opportunity to disapprove of the additional lanes, which will do nothing to alleviate congestion but will only enable worse speeding and safety issues and do further environmental harm to the surrounding community.

Response

This project has undergone an extensive review process. The MPO Policy Board approved the project on September 3, 2025, and an amendment to the project on February 4, 2026.

At Meetings

Public Comment

Would like to see (1) walkable neighborhoods with locally based goods and services, connected by rail-based public transportation, and (2) affordable housing that does not require use of an automobile to access goods and services.

Response

Project applications submitted to the MPO for federal funding receive a higher score when they improve the active transportation network and access to transit. Additional information is available on the MPO's Funding Programs webpage.

Was this page helpful to you? * required