Past Transportation Improvements

The following summarizes the status of major projects listed for 2025–2029 in the Madison Metropolitan Planning Area.

Roadway Projects

Project IDProjectImplementing AgencyStatusTotal Cost
1W. Verona Avenue (Legion Street Intersection)City of VeronaCompleted$355,000
3CTH G Mt. Vernon Cr. BridgeDane CountyCompleted$837,000
4CTH G West Branch Sugar River BridgeDane CountyCompleted$939,000
5CTH G West Branch Sugar River BridgeDane CountyCompleted$623,000
7STH 19 (Westmount Drive Intersection)WisDOTCompleted$2,802,000
8Main Street (Walker Way, Bird St., and Linnerud Dr.)City of Sun PrairieCompleted$979,000
11CTH BB Koshkonong Cr. BridgeDane CountyCompleted$777,000
12CTH MN Door Creek BridgeDane CountyCompleted$0
13CTH N Koshkonong Creek BridgeDane CountyCompleted$886,000
14CTH PQ Koshkonong Creek BridgeDane CountyCompleted$1,197,000
15CTH TT Maunesha River BridgeDane CountyCompleted$791,000
18S. Syene Road (McCoy Road Intersection)City of FitchburgCompleted$3,643,000
22CTH A Koshkonong Creek BridgeDane CountyCompleted$876,000
26USH 18/151 (CTH G to STH 69)WisDOTCompleted$0
30CTH A Saunders Cr. BridgeDane CountyCompleted$658,000
31CTH JJ Vermont Creek BridgeDane CountyCompleted$546,000
34Daentl Road (Token Creek Bridge, B-13-0096)Town of BurkeCompleted$640,000
38S. and W. Beltline (USH 12/14/18/151) (USH 14 to CTH N)WisDOTCompleted$0
41South Street (Hill Street to South Main Street)Village of DeForestCompleted$90,000
42Acker Parkway (Seminole Way to CTH CV)Village of DeForestCompleted$486,000
43S. Syene Road (Phase 1: Aurora Ave. to Nannyberry Park; Phase 2: Nannyberry Park to W. Clayton Rd.)City of FitchburgCompleted$3,798,000
45USH 12 (Parmenter St. to STH 19)WisDOTCompleted$0
46Interstate 39/90 (Janesville to Portage) (South Beltline to STH 30)WisDOTCompleted$0
47CTH CV (Lake Rd.) (STH 19 to Vinburn Rd.)Dane CountyCompleted$4,338,000
49Spring Hill Dr. (Lynn St. to Algonquin Dr.)City of MiddletonCompleted$302,000
51CTH V (E. North Street) (CTH CV to Nelson Court)Village of DeForestCompleted$1,064,000
52CTH V (E. North Street) (Stevenson Street to N. Halsor Street)Village of DeForestCompleted$447,000
54CTH V (Snowy Owl to CTH N)Dane CountyCompleted$4,428,000
56Interstate 94 Madison (CTH N to Airport Road)WisDOTCompleted$0
58Racetrack Rd. (USH 51 to CTH A)City of StoughtonCompleted$1,723,277
59Parmenter Street (450 Feet North of Century Ave. to Greenbriar Rd.)City of MiddletonCompleted$4,600,000
61STH 19 (Division Street in Waunakee to River Road in Westport)WisDOTCompleted$8,250,000
64Lynn Street (Knoll Court to Graber Road)City of MiddletonCompleted$64,000
81S. Fourth Street (Milwaukee St. to Isham St.)City of StoughtonCompleted$2,491,000
82Lincoln Ave. and Kriedeman Dr. (CTH B to Kriedeman Dr.; Lincoln Ave. to Page St.)City of StoughtonCompleted$2,105,000
83N. Thompson Road & St. Albert the Great Drive (W. Main St. to St. Albert the Great Drive; CTH C to N. Thompson Road)City of Sun PrairieCompleted$3,404,000
84E. Main Street (STH 19) (Bristol St. to Church St.; Dewey St. to Wood Violet Lane)City of Sun PrairieCompleted$2,544,000
87N. Bird Street (STH 19/Windsor Street to USH 151)City of Sun PrairieCompleted$1,715,000
91Vinburn Road (North Towne Rd. to CTH C)Village of WindsorCompleted$384,000
92N. Oak St. (Phase 1 – South) (E. Lincoln St. to Brook St.)Village of OregonCompleted$2,879,000
95E. Lincoln Street (N. Main St. to N. Perry Parkway)Village of OregonCompleted$2,657,000
104Creamery Road & Elvehjem Road (Milwaukee St. to CTH AB)Village of McFarlandCompleted$1,250,000
105Windsor Road (Charlie Grimm Road to CTH CV)Village of WindsorCompleted$0
106Interstate 39/90/94 (0.55 Miles S. of CTH V to NCL)WisDOTCompleted$16,023,000
118Stonefield Road (Gammon Road to Old Middleton Road)City of MiddletonCompleted$0
120Linnerud Drive (S. Walker Way to S. Bird Street)City of Sun PrairieCompleted$1,280,000
121S. Division Street (Knightsbridge to E. Main St.)Village of WaunakeeCompleted$825,000
129CTH N (Progress Way to NCL)Dane CountyCompleted$4,783,000
133CTH P (CTH PD to CTH S)Dane CountyCompleted$3,380,000
136Wilson Street (Van Buren St. to Lincoln Ave.)City of StoughtonCompleted$156,000
138Country View Road (900 Feet South of CTH PD to Future West Road)City of VeronaCompleted$26,000,000
244CTH AB (Buckeye Road) (WSOR RR Crossing)WisDOTCompleted$328,000
263Lacy Rd. & Seminole Hwy. (Seminole Hwy.: Lacy Road to Schuman Drive; Lacy Rd.: Seminole Hwy. East to Savanna Oaks MS)City of FitchburgCompleted$750,000
267Gammon Road & Watts Road (Intersection Improvements)City of MadisonCompleted$0
282Mark Drive (N. Nine Mound to Rita Ave.)City of VeronaCompleted$2,210,000
284Rita Avenue (Mark Drive to Plympton Street)City of VeronaCompleted$1,505,000
285Plympton Street (Rita Ave. to Westlawn Ave.)City of VeronaNew$810,000
292S. Main St. (State St. to S. Perry Pkwy.)Village of OregonCompleted$0
294Lake Kegonsa RoadTown of RutlandCompleted$0
44Broadway Drive (St. Albert the Great Dr. to Stonehaven Dr.)City of Sun PrairieRemoved$325,000
60Fish Hatchery Road (CTH D) (Sparkle Stone Crescent to 450 Feet S. of Byrneland Street)City of FitchburgRemoved$6,240,000
86Stonehaven Drive (Boulder Way to N. Bristol Street)City of Sun PrairieRemoved$115,000
103Bailey Road (Forward Dr. to Grove St./CTH N)Town of Sun PrairieRemoved$1,791,000
112USH 151 (Park Street) (Badger Road to W. Washington Ave.)WisDOTRemoved$12,227,000
256Interstate 39/90 (Milwaukee Street Bridge)WisDOTRemoved$1,959,000
286N. Shuman Street (W. Harriet to Richard)City of VeronaRemoved$170,000
287Whalen Road (Military Ridge Drive to East City Limits)City of VeronaRemoved$0
291CTH V (W. North St.)Village of DeForestRemoved$0
707Irish Lane (S. Fish Hatchery Road to S. Syene Road)City of FitchburgRemoved$2,635,000
789Nelson Road (WSOR RR Crossing)WisDOTRemoved$385,000

Bicycle and Pedestrian Projects

Project IDProjectImplementing AgencyStatusTotal Cost
156USH 51 Pedestrian UnderpassCity of StoughtonCompleted$1,624,000
158USH 51 UnderpassWisDOTCompleted$0
160West Verona Ave. & Westlawn Ave. RRFBCity of VeronaCompleted$74,000
164E. Taylor/Weald Bridge/Main St. (CTH N) Intersection ImprovementVillage of Cottage GroveCompleted$500,000
171Badger Rusk PathCity of MadisonCompleted$1,111,000
172N. Bird Street Path and RRFBs (Existing Path to 1,280 Feet S. of Egre Road)City of Sun PrairieCompleted$363,000
173S. Fourth St. Corridor Path (Milwaukee St. to Isham St.)City of StoughtonCompleted$0
174N. Bird St. Corridor Path (STH 19 to USH 151)City of Sun PrairieCompleted$0
175Windsor Road Path (Charlie Grimm Road to CTH V)Village of WindsorCompleted$0
197S. Syene Road Bike Lanes (E. Cheryl Pkwy. to W. Clayton St.)City of FitchburgCompleted$0
198Tancho Drive Path (Tancho Dr. to USH 151)City of MadisonCompleted$0
200CTH BB Bike Path Extension (Southing Grange to CTH N)Village of Cottage GroveCompleted$400,000
202South Loop Trail Extension (Lowell Park to Magnolia Meadows)City of StoughtonCompleted$450,000
210CTH BB/Buss Road Path and Intersection ImprovementVillage of Cottage GroveCompleted$550,000
295Capital City Trail Hydrology Study and ImprovementsDane CountyCompleted$0
313Safe Routes to School PlanCity of MadisonCompleted$150,000
318Cayuga Connector Path (Parmenter St./Discovery Dr./USH 12 Roundabout to University Ave./Cayuga St.)City of MiddletonCompleted$0
320Yahara River Trail (4th St. to River Park)City of StoughtonCompleted$0
332North Street (CTH V) Corridor Path (Stokely Dr. to Main St.)Village of DeForestCompleted$0
336Village of Oregon Bicycle & Pedestrian Transportation StudyVillage of OregonCompleted$76,000
356Belleville Schools Safe Routes Path (Study)Village of BellevilleCompleted$0
176Fitchrona Road Bike Lanes and Path (Lacy Rd. to Nesbitt Rd.)City of FitchburgRemoved$0
185Stone Quarry Rd. Trail (Columbus St. to the Patrick Marsh Wildlife Area)City of Sun PrairieRemoved$430,000
193Fitchrona Road Bike Lanes (North of Whalen to South of Whalen)City of FitchburgRemoved$0
199CTH C Multi-Use Path Gap (St. Albert the Great Dr. to Shonas Highlands Park Path)City of Sun PrairieRemoved$148,000
205Path Connection Through ThadenVillage of Cottage GroveRemoved$330,000
206Westlawn Dr. Bike Improvements (CTH BB to W. Oak St.)Village of Cottage GroveRemoved$350,000
207Path Connection to McCarthy ParkVillage of Cottage GroveRemoved$200,000
209W. Oak St. Bike Improvements (Westlawn Dr. to CTH BB)Village of Cottage GroveRemoved$115,000
211Park St. Connector Trail (Perry Pkwy. to Janesville St.)Village of OregonRemoved$150,000
311Old Sauk Trail OverpassCity of MadisonRemoved$0
322Katherine Dr. Sidewalk (Mockingbird Ln. to Schuster Rd.)City of Sun PrairieRemoved$75,000
324Patrick Marsh Trail Link (Stone Quarry Rd. to Town Hall Dr. Path)City of Sun PrairieRemoved$506,000
326Sheehan Park Scenic Point Trail Link (Sheehan Park to Heritage Court)City of Sun PrairieRemoved$0
331Connect Town/Village Streets With Path(s)Village of Cottage GroveRemoved$110,000
355Off-Street Path ReplacementCity of Sun PrairieRemoved$500,000

Transit Projects

Project IDProjectImplementing AgencyStatusTotal Cost
810Job Ride Program (Transit Operating)YWCA TransitCompleted$592,000
218Transit Shuttle (Transit Capital)City of FitchburgRemoved$87,000
357Transit Shuttle Operations (Transit Operating)City of FitchburgRemoved$184,000

Parking Projects

Project IDProjectImplementing AgencyStatusTotal Cost
215State Street Campus–Lake Street Parking GarageCity of MadisonCompleted$0
216Intercity Bus TerminalCity of MadisonCompleted$0
368Parking Utility Vehicle ReplacementCity of MadisonRemoved$0

Other Projects

Project IDProjectImplementing AgencyStatusTotal Cost
734Fire Engine Emissions MitigationCity of Sun PrairieRemoved$122,000

Transportation Demand Management (TDM)

MPO team members smiling at a RoundTrip table for Madison Bike Week Commuter Station in Fitchburg
RoundTrip Program Manager Zia Brucaya and MPO Marketing & Communications Specialist Kayla Haas staff a table at a Bike Week event in Fitchburg.

The MPO's TDM program, RoundTrip, coordinates the activities of various agencies and organizations to encourage alternatives to driving alone, including carpooling, vanpooling, public transit, bicycling, and walking. These efforts help reduce driving and traffic congestion on major corridors and around work sites.

Through RoundTrip, MPO staff assist employers with resources such as on-site visits, promotional materials, toolkits, employee surveys, and branded networks on the ride-matching website.

RoundTrip partners with Dane County, Metro Transit, and UW–Madison on an annual advertising campaign to build public awareness. Staff also respond to requests for assistance by email and phone.

RoundTrip also partners with Dane County to administer the Dane County Emergency Ride Home program and manages a website and an online ride-matching and trip-planning platform connected to a statewide database.

TDM Project Status

Transportation Options, Employer Programs, and Parking

ProjectStatusImplementing Agency
Regional Transportation Options Program (RoundTrip)

Ongoing. Coordinates ridesharing and partners with WisDOT and SEWRPC to administer the statewide rideshare platform serving all three programs.

Administers the Dane County Emergency Ride Home program, Dane County Employee Bus Pass Program, and two annual transportation challenges. Conducts an annual advertising campaign jointly funded by the MPO, UW–Madison, Dane County, and Metro Transit.

MPO
State Vanpool Program

Ongoing. Wisconsin Department of Administration transferred program management to Commute with Enterprise in May 2023. 

Vans are open to non-state riders. Participation remains well below pre-pandemic levels, partly due to hybrid work schedules and increased rider costs.

Wisconsin Department of Administration 
Residential Parking PermitsOngoing. Covers most central Madison neighborhoods.City of Madison
Downtown Parking ManagementOngoing. Dane County employees who primarily use alternatives to driving alone receive free parking in the county ramp.Dane County
TDM OrdinancesOngoing. Madison launched an ordinance-backed TDM program in 2023, applying transportation demand management requirements to new and expanding developments during the development approval process.City of Madison
Employer TDM Programs

Ongoing. Strategies include flexible parking, shuttle services, and bus passes. UW–Madison's Commuter Solutions program moved its Emergency Ride Home program delivery to the RoundTrip platform in 2026. 

Dane County's Employee Options program provides a free bus pass, free occasional parking for employees who do not commute alone by car, and a free Capital City State Trail pass for bicycle commuters.

UW–Madison, Dane County
Employer Bus Pass Programs

Ongoing. Metro offers seven Employer & Campus Pass programs providing unlimited rides at discounted rates for City of Madison employees; Dane County employees; Edgewood University students and faculty; Madison College students; UW–Madison students, employees, and hospital employees; UPH Meriter Hospital employees; and St. Mary's Hospital employees. 

Metro's Commute Card program also provides discounted unlimited rides through participating businesses, capped at $65 per month.

Hospitals, City and County Government, Universities and Colleges, and Other Employers

Transit Services, Infrastructure, and Fares

ProjectStatusImplementing Agency
Transit Priority Infrastructure

Madison began budgeting for transit improvements in priority areas in 2022, including bus queue jumps. 

Bus lanes and other priority treatments were completed with East-West bus rapid transit (BRT) construction in 2024. North-South BRT improvements are in design in 2026.

City of Madison
Transit Service Enhancements, Including Fixed-Guideway Service

Buses are purchased according to the fleet replacement schedule. Service was reduced in 2020 due to COVID-19, followed by minor improvements and no changes in 2022. 

A redesigned service network launched in June 2023, greatly increasing job access for most residents. East-West BRT service began in 2024. North-South BRT improvements are in design in 2026.

Metro Transit
Bus Service to Outlying Employment Centers

Ongoing. Verona commuter service expanded in 2012, 2014, and 2023. 

Service improved to American Center in 2015 and began serving the Exact Sciences facility in 2018. Sun Prairie service began in 2019 and expanded in 2023 to serve the entire community with two local routes. 

The June 2023 Network Redesign improved service to outlying employment areas. Service expanded to Monona in 2025, and Verona service increased to all-day service in 2026.

Metro Transit
Transit AmenitiesOngoing. Includes signs, shelters, and other transit amenities.Metro Transit
Downtown Shuttle Service and Free Fare ZoneDowntown Shuttle: Ended in 1987, resumed with the 1998 route restructuring, and ended again in 2000. Midday service between the UW campus and Capitol Square began in 2004 and has since been provided through overlapping routes. 
Free Fare Zone: Operated downtown from 1991 to 1998.
Metro Transit
Transit Service to Surrounding Communities

Epic Systems commuter service in Verona began in 2005 and improved in 2012, 2014, 2023, and 2026. 

Express service between Madison and Sun Prairie began in 2019 and became an extension of Route A in 2023. Local buses replaced Sun Prairie's shared-ride taxi service in September 2023. 

The MPO helped Oregon evaluate service models in 2022–2023 and DeForest in 2023. Metro contracted with Monona for service in 2025. Potential expansion to Cottage Grove is under discussion, with timing to be determined.

Metro Transit, Private Transit Services, Municipalities
Transit Fares and Bus Pass Programs

Ongoing. A 2009 fare increase supported the system and expanded service hours. 

A fare payment technology and policies study was conducted in 2021–2022. Launched in 2024, the Fast Fare card system provides daily, weekly, and monthly fare caps. Cards can be reloaded online, at BRT kiosks, and at many area businesses.

Metro Transit

Transportation Operations, Technology, and Incident Management

ProjectStatusImplementing Agency
Transportation Monitoring and Customer Information

Ongoing. Intelligent transportation systems (ITS) include bus location tracking, real-time arrival information, automatic passenger counters, and security cameras. Real-time traffic information is available through apps, the 511 website, and cameras. 

Technology upgrades beginning in 2021 included real-time fleet communications, on-bus systems, and scheduling and maintenance systems. A new Metro Bus Tracker app and webpage launched in 2024.

Metro Transit, WisDOT, City of Madison
Transit and Traffic Operations Improvements

Ongoing. Includes traffic signal coordination, advanced traffic control systems, intersection reconfiguration, interchange ramp and auxiliary lane improvements, ramp meters, real-time information, and bus priority treatments. 

Adaptive signals were installed on CTH PD/Fish Hatchery Road as part of the Verona Road/Beltline project, on University Avenue in 2020, and on E. Washington Avenue in late 2020. 

The first bus queue jump was added at eastbound E. Washington Avenue/Fourth Street. East-West BRT added queue jumps, traffic signal priority, and bus-only lanes in 2024.

WisDOT and Local Implementing Agencies
Highway Incident ManagementOngoing on the Beltline and Interstate. Includes traffic signal systems, message signs, and service patrols. The Beltline flex lane west of Whitney Way opened in 2022.WisDOT

Bicycle and Pedestrian Improvements

ProjectStatusImplementing Agency
Bikeway System Improvements

Ongoing. A comprehensive bicycle plan was completed in 2015, followed by a bicycle wayfinding plan in 2017, with implementation continuing. The bikeway system plan is updated through Regional Transportation Plan updates. 

The MPO adopted its Active Transportation Plan in 2026. Fitchburg, Middleton, and Sun Prairie adopted bicycle, pedestrian, or active transportation plans in 2025–2026. Madison's Safe Routes to School, Pedestrian, and Bike Network plans are moving toward adoption in 2026.

Municipalities, Dane County, WisDOT

Air Quality Impacts

Under the National Ambient Air Quality Standards (NAAQS) included in the Clean Air Act Amendments (CAAA) of 1977, Dane County was briefly designated a “non-attainment" area for photochemical oxidants. The Act required states to develop revised State Implementation Plans to bring non-attainment areas into compliance with air quality standards by the end of 1982.

The State designated the Dane County Regional Planning Commission (DCRPC) to lead the development of a plan to bring Dane County into compliance with the photochemical oxidant standards. The DCRPC adopted this plan, “Transportation/Air Quality Planning for the Dane County Area," in April 1979. The “non-attainment" designation was removed in late 1982.

The 1990 Clean Air Act Amendments were signed into law in November 1990. Under the revised Act, the two major areas of concern for Dane County are maintaining attainment status and complying with emission restrictions and engine regulations for transit vehicles purchased by public and private transit operators after 1990.

To date, the State of Wisconsin has mandated the implementation of most available low-cost control techniques and has made considerable progress in controlling industrial emissions and other stationary sources. Controlling mobile sources, however, will play a major role in future efforts.

In addition to emission reductions from cleaner vehicles, transportation system management (TSM) and transportation demand management (TDM) measures can help reduce motor vehicle emissions by slowing growth in vehicle miles traveled. 

These measures include:

  • Traffic flow improvements
  • Carpooling and employer demand management programs
  • Improved public transit and pedestrian and bicycle facilities
  • Parking management
  • Special event planning

The Madison area has a long-standing commitment to implementing TDM and TSM measures to improve the overall efficiency of the transportation system. The transportation/air quality plan for Dane County identified 17 TDM/TSM projects for implementation during the 1979–1982 period and established goals for reducing volatile organic compounds through these measures.

All recommended projects were initiated, and several were completed. Many continue as ongoing projects, and new projects have been added, as noted above.