Knutson Drive Reconstruction

April 8, 2024 Update

The design team is working toward final design and anticipates the project be placed for contractor bids this spring. 

The design team is also working with the City Real Estate team to acquire Temporary Limited Easements (TLEs) during construction to allow space for the contractor to build the sidewalk. The TLEs are required for some properties on Knutson Drive between Green Avenue and Northport Drive and are temporary for construction. Once construction is complete, the TLEs expire. The City Surveyor completed Right-of-Way and TLE field staking at the end of March as part of the Real Estate process to acquire TLEs.

View past project updates »

Project Details

  • Location

    • 321 Knutson Drive
      Madison, WI 53704
  • Status

    In Design
  • Estimated Schedule

  • Impact

    Major
  • Alder District

    District 18
  • Contract Number

Project Information

Project Overview

The City is planning to reconstruct Knutson Drive (Green Avenue to Northport Drive). The project includes a new street design with curb and gutter, sidewalk, and driveway aprons. The asphalt pavement and gravel base will be replaced. The sanitary sewer and water main will remain. The project will add storm sewer and stormwater features for controlling surface water runoff.

The City is planning to resurface Knutson Drive (Heffernan Drive/Beilfuss Drive to Green Avenue). The project includes installing storm sewer from Heffernan Drive to Knutson Drive east of Green Avenue and remove and replace the asphalt pavement. 

The City is planning to resurface Green Avenue (Harper Road to Knutson Drive). The project includes removing and replacing a portion of the asphalt pavement.

map

Knutson Drive (Green Avenue to Northport Drive) Improvement Options:

Option #1A: The proposed street width will be 21-feet (11-feet eastbound and 10-feet westbound) from face of curb to face of curb with two 8-foot parking pockets along the street. The first parking pocket is west of Westport Road on the south side of the street and is 60-feet accommodating 4 spaces. The second parking pocket is east of Westport Road on the south of the street 75-feet accommodating 5 spaces.  By keeping the street at the existing width, this layout supports lowering vehicle speeds, which was noted as a priority for the neighborhood in the previous survey and the first public meeting, as well as preserves some of the trees in the right-of-way. This option would result in fewer on-street parking stalls, but previous input from the community identified on-street parking as a lower priority. This option is currently the City staff recommendation.

Knutson Drive Option
Knutson 1A

 

Option #1B: Knutson Drive from Green Avenue to Westport Drive (21-feet (11-feet eastbound and 10-feet westbound) and Knutson Drive from Westport Drive to Northport Drive (2-11’ lanes vehicle lanes, 2-7’ bicycle lanes, and 5’ sidewalks on both sides). The block between Green Avenue and Westport Drive would have 8’ parking pockets (same as option 1A) with no bicycle lanes and supports lowering speeds and preserving trees in the right-of-way. The block between Westport Drive and Northport Drive would have bike lanes, which are being considered due to higher traffic volumes on this block, but this would require a wider pavement than Option 1A. Curb and gutter would be included with both layouts. 

Knutson Drive, Green Avenue to Westport Drive
 

Knutson Drive Option
Knutson 1B

Knutson Drive, Westport Drive to Northport Drive

Knutson Drive Option
Knutson Drive Option

Option #2A: Knutson Drive from Green Avenue to Northport Drive (2-11’ vehicle lanes, 2-8’ parking lanes, and 5’ sidewalks on both sides). This layout has wider pavement than Option 1A & 1B, which is more likely to result in higher vehicle speeds, but this option would allow for more on-street parking. This option also removes all trees in the right-of-way. Curb and gutter would be included with the layout.

Knutson Drive Option
Knutson Drive Option

Option #2B: Knutson Drive from Green Avenue to Westport Drive (2-11’ vehicle lanes, 2-8’ parking lanes, and 5’ sidewalks on both sides) and Knutson Drive from Westport Drive to Northport Drive (2-11’ lanes vehicle lanes, 2-7’ bicycle lanes, and 5’ sidewalks on both sides). Similar to 2A, this layout is more likely to result in higher vehicle speeds due to the wider pavement, but provides more on-street parking than Option 1A & 1B, and also has bike facilities between Westport and Northport. This option also removes all trees in the right-of-way. Curb and gutter would be included with both layouts.

Knutson Drive, Green Avenue to Westport Drive

Knutson Drive Option
Knutson Drive Option

Knutson Drive, Westport Drive to Northport

Knutson Drive Option
Knutson Drive Option

Project Limits

Knutson Drive Reconstruction – Green Avenue to Northport Drive

Knutson Drive Resurfacing – Heffernan Drive/Beilfuss Drive to Green Avenue

Green Avenue Resurfacing – Knutson Drive to Harper Road

Project Schedule

Design: Summer/Fall/Winter 2023 & Winter/Spring 2024

Bids Advertised: Spring 2024

Construction: Start Late Summer - End Fall 2024 or Start Late Summer - End Late Spring 2025, depending on what the Contractor decides

Public Involvement

There are a number of points of contact during this project where the public is encouraged to give feedback as part of public information meetings and public hearings. Dates, times and locations are indicated below:

Public Information Meetings 

Survey

Mailings

Public Informational Meeting:  Letter to property owners; Postcard to nearby residents (both mailed Sept. 6, 2023)

Board of Public Works Hearing February 21, 2024: Notice of Meeting, Fact and Details Sheet, Schedule of Assessments

City Process, Meetings

Transportation Commission: Dec. 13, 2023, option 1A recommended

Board of Public Works: February 21, 2024, option 1A approved

Common Council: March 5, 2025, approval pending
 

Project Updates

The design team is working toward final design and anticipates the project be placed for contractor bids this spring. 

The design team is also working with the City Real Estate team to acquire Temporary Limited Easements (TLEs) during construction to allow space for the contractor to build the sidewalk. The TLEs are required for some properties on Knutson Drive between Green Avenue and Northport Drive and are temporary for construction. Once construction is complete, the TLEs expire. The City Surveyor completed Right-of-Way and TLE field staking at the end of March as part of the Real Estate process to acquire TLEs.

The design team continues with the preliminary design. The assessment information was mailed out and the Board of Public works approved option 1A. The design team has also involved the City Real Estate team to acquire Temporary Limited Easements (TLEs) during construction to allow space for the contractor to build the sidewalk. The TLEs are required for some properties on Knutson Drive between Green Avenue and Northport Drive and are temporary for construction. Once construction is complete, the TLEs expire. The City Real Estate team will be reaching out to properties owners in 2024.

The design team continues with the preliminary design and work on preparing the preliminary schedule of assessments for mailing to residents in early 2024. The design team has also involved the City Real Estate team to acquire Temporary Limited Easements (TLEs) during construction to allow space for the contractor to build the sidewalk. The TLEs are required for some properties on Knutson Drive between Green Avenue and Northport Drive and are temporary for construction. Once construction is complete, the TLEs expire. The City Real Estate team will be reaching out to properties owners early in 2024.

 

Please review the project overview for Knutson Drive:

The design team presented the project design to the Transportation Commission on Dec. 13, 2023. The Transportation Commission recommend Option 1A with the change to remove 1 of the 3 parking pockets (see overview exhibits) included with option 1A. The design team will continue with the preliminary design and work on preparing the preliminary schedule of assessments for mailing to residents in early 2024.

The design team will attend and present the project design to the Transportation Commission on Dec. 13, 2023. After feedback from the public information meeting on Nov. 29, 2023, the design team will remove 1 of the 3 parking pockets (see overview exhibits) included with option 1A and 1 of the 2 parking pockets (see overview exhibits) included with option 1B as part of the presentation to the Transportation Commission. The design team will seek an option recommendation from the Transportation Commission.

 

See overview exhibits of each option:

 

Thank you to everyone who attended the Nov. 29, 2023 Public Information Meeting. The meeting materials are now available: 

A public information meeting has been scheduled for 6:30 p.m., Nov. 29, 2023, via Zoom. Registration prior is required. 
Nov. 29, 2023 Public Information Meeting Registration 
 

A survey is now available. Please take the survey before 5 p.m., Dec. 7, 2023. 
Knutson Drive Reconstruction- Green Avenue- Northport Drive Survey

Was this page helpful to you?