Lower Badger Mill Creek Pond
Last Updated: 10/06/2020
Latest Update
There is no update right now. This section will be updated with information when it's available.
Project Overview
The Stormwater Utility is proposing a project to construct a series of regional detention basins north of Mid-Town Road, and east of Meadow Road. The purpose of the ponds will be to contain flood water, reducing downstream flooding and minimizing local flood impacts.
As part of the project City Engineering is proposing to extend Feather Edge Road from the existing terminus to Meadow Road. The City Parks Division will also be discussing a future master planning effort for the proposed Hill Creek Park expansion.
Project Schedule
Final Design – Summer/Fall 2020
Construction – 2021
Pertinent meetings dates, such as Board of Public Works and Common Council, will be posted on this project page.
Public Involvement
There are a number of points of contact during this project where the public is encouraged to give feedback as part of public information meetings and public hearings. Dates and times are indicated below:
Public Information Meetings
Two public information meetings were held for this project.
July 16, 2020 Public Information Meeting PowerPoint Presentation
May 23, 2018 Public Information Meeting PowerPoint Presentation
City Meetings, Process
Board of Public Works
Information will be posted when available.
Common Council
Information will be posted when available.