Sidewalk Replacement Program
Project Details
Project Information
Latest Update
5/3/2023 Update:
Join us today virtually: The public information meeting for District 12 Sidewalk Replacement Program has been scheduled for 5:30 p.m., May 3, 2023, via Zoom. Registration prior is required.
May 3, 2023 Public Information Meeting Registration
May 3, 2023 Public Information Meeting PowerPoint Presentation
Sidewalk replacement is underway within District 18 (contract #8706). The contractor (Speedway Sand and Gravel) is currently working in Ward 35, in the Comanche Way area north of Wheeler Rd. Saw cutting of trip hazards in District 18 (contract #8713) will occur later this summer. The contractor (Universal Concrete Grinding) is currently working on another project and will not be available until August.
Sidewalk replacement in District 12 (contract #8705) will begin soon. Pending final contract approval, the contractor (Raymond P Cattell, Inc) would like to start work the week of May 8th. Saw cutting of trip hazards in District 12 (contract #8697) has started. The contractor (Southern Wisconsin Construction) is currently working in Ward 28, in the Myrtle St/Coolidge St/Dahle St area north of Commercial Ave.
Project Overview
The Annual Sidewalk Replacement Program was created to identify and repair defects (cracks, broken sections, offsets creating trip hazards, ponding/icing issues) throughout the City, rotating through the alder districts on a 10-year cycle.
In 2023, the Sidewalk Replacement Program will be performing work within Aldermanic Districts 12 and 18.
Sidewalk sections marked with white arrows or X’s are designated for replacement. Sidewalk sections with tripping hazards, marked with a pink line across the joint and a white ‘C’, are designated for saw cutting. Separate contracts are bid for the replacement and the saw cutting.
- Criteria for Replacement of Public Sidewalk and Curb and Gutter
- Care and Restoration of Disturbed Turf Areas - Brochure
- Street Assessment Policy
- ADA Ramp Replacement Guidelines
Project Limits
Each cycle focuses on different districts. In 2023, sidewalk sections will be repaired and replaced throughout Aldermanic Districts 12 & 18.
Project Schedule
District 18: 04/17/2023 to 09/15/2023
District 12: 05/15/2023 to 10/06/2023
Public Involvement
There are a number of points of contact during this project where the public is encouraged to give feedback as part of public information meetings and public hearings. Dates, times and locations are indicated below:
Public Information Meetings
The public information meeting for District 12 Sidewalk Replacement Program has been scheduled for 5:30 p.m., May 3, 2023, via Zoom. Registration prior is required.
May 3, 2023 Public Information Meeting Registration
May 3, 2023 Public Information Meeting PowerPoint Presentation
April 5, 2023 Public Information Meeting Recording
April 5, 2023 Public Information Meeting PowerPoint Presentation
District 18 Map
District 12 Map
The public information meeting for work within District 12 has not been scheduled yet. A registration link will be posted when a date is scheduled.
If you need an interpreter, translator, materials in alternate formats or other accommodations to access this service, activity or program, please call Bill McGlynn of the Engineering Division at 608-266-4537.
Si necesita un intérprete, un traductor, materiales en formatos alternativos u otros arreglos para acceder a este servicio, actividad o programa, comuníquese inmediatamente al número de teléfono que figura a continuación.
Yog tias koj xav tau ib tug neeg txhais lus, ib tug neeg txhais ntawv, cov ntaub ntawv ua lwm yam los sis lwm cov kev pab kom siv tau qhov kev pab, kev ua num los sis kev pab cuam no, thov hu rau tus xov tooj hauv qab no tam sim no.
City Process, Meetings
Common Council: 02/07/223
Board of Public Works: 01/18/2023
Sidewalk Repair Schedule by Alder District
Year | Alder District & Ward |
---|---|
2017 | Districts 15 & 17 |
2018 | Districts 3 & 16 |
2019 | Districts 1, 7 & 9 |
2020 | Districts 4 & 8 |
2021 | Districts 13 & 14 District 14:
District 13: |
2022 | District 5 |
2023 | Districts 12 & 18 |
2024 | District 11 & 19 |
2025 | District 10* & 20 (*Except District 10, Ward 79. Previously District 14, Ward 75 completed in 2021) |
2026 | District 2 & 6 |
2027 | District 3 & 17 |
2028 | District 15 & 16 |
2029 | District 1 & 9 |
2030 | District 4 & 13 (Census) |
2031 | District 5 & 8 |
2032 | District 7 & 20 |
2033 | District 10 & 14 |
2034 | District 12 & 18 |
2035 | District 11 & 19 |
2036 | District 2 & 6 |
2037 | District 3 & 17 |
2038 | District 15 & 16 |
2039 | District 1 & 9 |
2040 | District 4 & 13 (Census) |
2041 | District 5 & 8 |
Forms
List of Prequalified Contractors
Related Ordinances, Statutes, & Administrative Procedures
- Madison General Code of Ordinances:
Sidewalks addressed by Section 10.06 & 10.09 - Wisconsin Statutes - Sidewalks addressed by Section 66.0907, Wisconsin State Legislature
- Street Patching Criteria
- Terrace Treatment Policy