Last Updated: 04/27/2017

Dist 15: Tentative contract start date is May 30.

Dist 17: Tentative contract start date is May 15.

At this time we don't know where the contractors will start working in either district.  Once we have more details on their schedule, the website will be updated.

General Information:

Sidewalk Repair Schedule by Aldermanic District:
Year Aldermanic District & Ward
2014

Districts 11 & 19

2015

Districts 10 & 20

2016 Districts 2 & 6
2017 Districts 15 & 17
2018 Districts 3 & 16
2019 Districts 1, 7 & 9
2020 Districts 4 & 8
2021 Districts 13 & 14
2022 District 5
2023 Districts 12 & 18

Forms:

List of  Prequalified Contractors