University Avenue

June 24, 2024 Update

Work the Week of June 24, 2024

Minor concrete sidewalk and curb installation and repair will be taking place at various locations during the week.

The contractor will continue final cleanup and restoration work throughout the project limits.  

Off-peak (9 AM – 3 PM) single-lane closures in both the westbound and eastbound directions on University Ave. will occur during the week. The closures are necessary to allow access for workers to complete a final review and perform final adjustments of the underground utilities installed beneath the roadway.

Work the Week of July 1, 2024

The contractor intends to complete all final clean up and restoration work throughout the project limits and will begin removing traffic control devices from University Ave. and adjacent side streets.

The pedestrian overpass at University Bay Drive is scheduled to receive a final coat of protective surface treatment. The overpass will be sealed one half at a time while maintaining foot and bicycle traffic; however, the operating width of the overpass will be reduced in the areas where the surface treatment is being applied.

Please note that the Bus Rapid Transit (BRT) project will be continuing work on the bus stations within the University Ave. project limits. The BRT project’s ongoing work may require periodic lane closures or other traffic restrictions.

Traffic/Pedestrian/Bike Impacts

Traffic will remain in a configuration that maintains at least two lanes in both directions during peak travel periods on University Ave. within the project limits (from approximately Shorewood Blvd. to University Bay Dr.). Short-term sidewalk detours along University Ave. and adjacent side streets may be needed to complete the remaining sidewalk and pedestrian ramps. Please be alert for sidewalk closed and pedestrian detour signage that will be in place while this work is being completed. Also note that the Bus Rapid Transit (BRT) project is utilizing single-lane closures east and west of the University Ave. project limits. additional information on work related to the BRT project can be found here: https://www.cityofmadison.com/metro/routes-schedules/bus-rapid-transit

Note that the work is weather dependent and may be subject to change.

View the full University Avenue Weekly Update.

View past project updates »

Project Details

  • Location

    • 2737 University Avenue
      Madison, WI 53705
  • Project Type

  • Status

    Construction
  • Estimated Schedule

  • Alder District

    District 5

Project Information

Project Overview

University Ave is scheduled for reconstruction from Shorewood Boulevard/Hill St to University Bay Drive/Farley Ave. The City of Madison is jointly participating with the Village of Shorewood Hills on the design and construction. The project includes reconstruction of pavement, curb and gutter, sidewalk as necessary, street lighting, traffic signals, water main, sanitary sewer and storm sewer.  Alternatives to improve pedestrian & bicycle connectivity, bus rapid transit initiatives and stormwater drainage have been reviewed, and the project plans have been updated to include a new pedestrian & bike overpass of University Bay Dr., a widened sidewalk along the southerly side of University Ave., and a 96-inch storm sewer pipe to help improve drainage in the area.  The project continues to be coordinated with the City’s planning efforts for bus rapid transit.

Full Project Map
Typical Section Example
University Bay Overpass Alternative
Project Fact and Details Sheet

Proposed improvments university bay

View a larger image of proposed improvements

Project Limits

Shorewood Boulevard/Hill St to University Bay Drive/Farley Ave.

Project Limits Map

Project Schedule

Construction is scheduled for 2022.

Public Involvement

There are a number of points of contact during this project where the public is encouraged to give feedback as part of public information meetings and public hearings. Dates and times are indicated below:

Public Information Meetings

City Meetings, Process

Board of Public Works: June 16, 2021

Transportation Commission: April 15, 2020

Common Council: July 6, 2021

Mailings

Extension of work hours for Construction Activities (Starting around Aug. 15, 2022)

Project Updates

Was this page helpful to you?