University Avenue

November 26, 2023 Update

Work the Week of Nov. 27, 2023 

On November 22, 2023, the traffic configuration on University Ave. was changed to a condition that moved the two eastbound lanes to be moved onto the newly completed asphalt pavement on the south side of the roadway. University Avenue Traffic Configuration (Anticipated 11-22-23).pdf

Curb and gutter work and installation of street lighting fixtures and traffic signals in the medians along University Ave. will continue throughout the week. 

The contractor anticipates changing traffic into the overwinter configuration on December 2, 2023. The overwinter condition opens all lanes on University Ave. and side streets with a temporary median divider between the eastbound and westbound lanes on University Ave.

Please note that off-peak single lane closures will be required in both directions on University Ave. in order to switch traffic into the overwinter traffic configuration. 

 

Work the Week of Dec. 4, 2023 

The contractor will complete work for the 2023 construction season on Ridge Street, Franklin Ave. and Schmitt Pl. and install temporary pavement at these side streets for the overwinter condition. 

Traffic signal components will be installed at the intersections of University Ave. and Shorewood Blvd. and University Ave. and University Bay Dr. Please note that the temporary traffic signals will continue to be utilized at these intersections while permanent traffic signal work are being installed and tested. 

 

Traffic/Pedestrian/Bike Impacts

Traffic is anticipated to change into an overwinter condition on approximately December 2, 2023. Single lane closures and/or traffic flagging operations on University Ave., as well as side streets, may be required during off-peak travel periods (9 AM to 3 PM). Sidewalk and pedestrian crosswalk adjustments, as well as minor changes to Madison Metro Transit bus stop locations, will occur periodically. Please note that Madison Bus Rapid Transit (BRT) work is scheduled to begin within the University Ave. project limits starting December 4, 2023. Updates on work related to the BRT project can be found here: https://www.cityofmadison.com/metro/routes-schedules/bus-rapid-transit  Note that the work is weather dependent and may be subject to change.

View past project updates »

Project Details

  • Location

    • 2737 University Avenue
      Madison, WI 53705
  • Project Type

  • Status

    Construction
  • Estimated Schedule

  • Alder District

    District 5

43.073607, -89.435334

Project Information

Project Overview

University Ave is scheduled for reconstruction from Shorewood Boulevard/Hill St to University Bay Drive/Farley Ave. The City of Madison is jointly participating with the Village of Shorewood Hills on the design and construction. The project includes reconstruction of pavement, curb and gutter, sidewalk as necessary, street lighting, traffic signals, water main, sanitary sewer and storm sewer.  Alternatives to improve pedestrian & bicycle connectivity, bus rapid transit initiatives and stormwater drainage have been reviewed, and the project plans have been updated to include a new pedestrian & bike overpass of University Bay Dr., a widened sidewalk along the southerly side of University Ave., and a 96-inch storm sewer pipe to help improve drainage in the area.  The project continues to be coordinated with the City’s planning efforts for bus rapid transit.

Full Project Map
Typical Section Example
University Bay Overpass Alternative
Project Fact and Details Sheet

Proposed improvments university bay

View a larger image of proposed improvements

Project Limits

Shorewood Boulevard/Hill St to University Bay Drive/Farley Ave.

Project Limits Map

Project Schedule

Construction is scheduled for 2022.

Public Involvement

There are a number of points of contact during this project where the public is encouraged to give feedback as part of public information meetings and public hearings. Dates and times are indicated below:

Public Information Meetings

City Meetings, Process

Board of Public Works: June 16, 2021

Transportation Commission: April 15, 2020

Common Council: July 6, 2021

Mailings

Extension of work hours for Construction Activities (Starting around Aug. 15, 2022)

Project Updates

Work the Week of Nov. 27, 2023 

On November 22, 2023, the traffic configuration on University Ave. was changed to a condition that moved the two eastbound lanes to be moved onto the newly completed asphalt pavement on the south side of the roadway. University Avenue Traffic Configuration (Anticipated 11-22-23).pdf

Curb and gutter work and installation of street lighting fixtures and traffic signals in the medians along University Ave. will continue throughout the week. 

The contractor anticipates changing traffic into the overwinter configuration on December 2, 2023. The overwinter condition opens all lanes on University Ave. and side streets with a temporary median divider between the eastbound and westbound lanes on University Ave.

Please note that off-peak single lane closures will be required in both directions on University Ave. in order to switch traffic into the overwinter traffic configuration. 

 

Work the Week of Dec. 4, 2023 

The contractor will complete work for the 2023 construction season on Ridge Street, Franklin Ave. and Schmitt Pl. and install temporary pavement at these side streets for the overwinter condition. 

Traffic signal components will be installed at the intersections of University Ave. and Shorewood Blvd. and University Ave. and University Bay Dr. Please note that the temporary traffic signals will continue to be utilized at these intersections while permanent traffic signal work are being installed and tested. 

 

Traffic/Pedestrian/Bike Impacts

Traffic is anticipated to change into an overwinter condition on approximately December 2, 2023. Single lane closures and/or traffic flagging operations on University Ave., as well as side streets, may be required during off-peak travel periods (9 AM to 3 PM). Sidewalk and pedestrian crosswalk adjustments, as well as minor changes to Madison Metro Transit bus stop locations, will occur periodically. Please note that Madison Bus Rapid Transit (BRT) work is scheduled to begin within the University Ave. project limits starting December 4, 2023. Updates on work related to the BRT project can be found here: https://www.cityofmadison.com/metro/routes-schedules/bus-rapid-transit  Note that the work is weather dependent and may be subject to change.

Work the Week of Nov. 20, 2023 

The contractor anticipates changing the traffic configuration on University Ave. to a condition that requires the two eastbound lanes to be moved onto the newly completed asphalt pavement on the south side of the roadway. 

Once traffic has shifted, curb and gutter work and installation of street lighting fixtures and traffic signals in the medians along University Ave. will begin. 

Concrete curb and sidewalk installation on the south side of University Ave. has been completed; however, there are a few remaining sidewalk gaps and temporary sidewalk installations that will need to be completed during the week. 

Permanent asphalt pavement has been completed for the new eastbound lanes on University Ave. as well as on Farley Ave. 

Please note that short-term traffic flagging, reduced roadway widths, and temporary lane shifts may be necessary while the contractor completes roadway grading and placement of asphalt at Franklin Ave., Ridge St., and Schmitt Pl. 

 

Work the Week of Nov. 27, 2023 

Installation of temporary and permanent curb will continue in the medians of University Ave. in preparation for the over-winter traffic configuration. 

Installation of street lighting fixtures will continue throughout the week.

Traffic signal components will be installed at the intersections of University Ave. and Shorewood Blvd. and University Ave. and University Bay Dr. Please note that the temporary traffic signals will continue to be utilized at these intersections while permanent traffic signal work are being installed and tested. 

 

Traffic/Pedestrian/Bike Impacts

Traffic is anticipated to change into a new configuration on approximately November 22, 2023. Single lane closures and/or traffic flagging operations on University Ave., as well as side streets, may be required during off-peak travel periods (9 AM to 3 PM). Sidewalk and pedestrian crosswalk adjustments, as well as minor changes to Madison Metro Transit bus stop locations, will occur periodically. Please note that Madison Bus Rapid Transit (BRT) work is scheduled to begin within the University Ave. project limits starting December 4, 2023. Updates on work related to the BRT project can be found here: https://www.cityofmadison.com/metro/routes-schedules/bus-rapid-transit  Note that the work is weather dependent and may be subject to change.

View the University Avenue Weekly Update:

 

Work the Week of Nov. 13, 2023 

Concrete curb and sidewalk installation on the south side of University Ave. is anticipated to continue between Schmitt Pl. and Farley Ave. Access to businesses will be maintained during this work; however, please note that available driveway widths may need to be reduced while the concrete is being placed and cured. 

Asphalt pavement will be placed for the new eastbound lanes of University Ave. between Schmitt Pl. and Franklin Ave. Asphalt paving will also be completed on Farley Ave. 

Installation of new sanitary sewer and water main between Schmitt Pl. and Farley Ave. has been completed.

Storm sewer connections and water main tie-ins at side streets on the south side of University Ave. will be completed during the week.

Installation of new street lighting fixtures will continue to be installed in areas where curb, sidewalk, and asphalt paving have been completed. 

Please note that short-term traffic flagging, reduced roadway widths, and temporary lane shifts may be necessary while roadway grading and placement of asphalt at side streets on the south side of University Ave. 

Work the Week of Nov. 20, 2023 

The contractor anticipates changing the traffic configuration on University Ave. to a condition that requires the two eastbound lanes to be moved onto the newly completed asphalt pavement on the south side of the roadway. 

Installation of temporary and permanent curb will begin in the medians of University Ave. in preparation for the over-winter traffic configuration. 

Traffic/Pedestrian/Bike Impacts

Traffic is anticipated to remain in its current configuration until approximately November 20, 2023. Single lane closures and/or traffic flagging operations on University Ave. as well as side streets on the south side of University Ave. may be required during off-peak travel periods (9 AM to 3 PM). Sidewalk and pedestrian crosswalk adjustments, as well as minor changes to Madison Metro Transit bus stop locations, will occur periodically. Please be alert for sidewalk closed and sidewalk detour signage identifying pedestrian routes. Temporary bus stop signage will also be in place identifying any changes to bus stop locations. Note that the work is weather dependent and may be subject to change.

Concrete curb and sidewalk installation on the south side of University Ave. will continue during the week. Access to businesses will be maintained during this work; however, please note that available driveway widths may need to be reduced while the concrete is being placed and cured.

Installation of new storm sewer, sanitary sewer, and water main will continue between Schmitt Pl. and Farley Ave.

The contractor will continue performing roadway grading and placement of aggregates as the underground utilities and services are being completed.

Traffic/Pedestrian/Bike Impacts

Traffic is anticipated to remain in its current configuration until approximately November 17, 2023. Single lane closures and/or traffic flagging operations on University Ave. as well as side streets on the south side of University Ave. may be required during off-peak travel periods (9 AM to 3 PM). Sidewalk and pedestrian crosswalk adjustments, as well as minor changes to Madison Metro Transit bus stop locations, will occur periodically. Please be alert for sidewalk closed and sidewalk detour signage identifying pedestrian routes. Temporary bus stop signage will also be in place identifying any changes to bus stop locations. Note that the work is weather dependent and may be subject to change.

View the full University Weekly Update Flyer

Work the Week of Oct. 30, 2023

It is anticipated that traffic will remain in the current configuration until approximately November 17, 2023. View an overview of the Stage 4 traffic configuration.

A closure of Hill St. is scheduled to begin at 7 AM on November 3, 2023. Hill St. is scheduled to reopen by 7 PM on November 4, 2023. An overview showing access to local businesses and access for pedestrians can be viewed here: Hill Street Closure

Concrete curb and sidewalk installation on the south side of University Ave. is anticipated to continue at various locations throughout the project limits. Access to businesses will be maintained during this work; however, please note that available driveway widths may need to be reduced while the concrete is being placed and cured.

Installation of new storm sewer, sanitary sewer, and water main will continue between Schmitt Pl. and Farley Ave.

Permanent asphalt paving between Hill St. and Schmitt Pl. is anticipated to begin during the week.

Please note that short-term traffic flagging, reduced roadway widths and temporary lane shifts may be necessary while underground utilities are being installed at the side streets on the south side of University Ave.

Was this page helpful to you?