University Avenue
June 24, 2024 Update
Work the Week of June 24, 2024
Minor concrete sidewalk and curb installation and repair will be taking place at various locations during the week.
The contractor will continue final cleanup and restoration work throughout the project limits.
Off-peak (9 AM – 3 PM) single-lane closures in both the westbound and eastbound directions on University Ave. will occur during the week. The closures are necessary to allow access for workers to complete a final review and perform final adjustments of the underground utilities installed beneath the roadway.
Work the Week of July 1, 2024
The contractor intends to complete all final clean up and restoration work throughout the project limits and will begin removing traffic control devices from University Ave. and adjacent side streets.
The pedestrian overpass at University Bay Drive is scheduled to receive a final coat of protective surface treatment. The overpass will be sealed one half at a time while maintaining foot and bicycle traffic; however, the operating width of the overpass will be reduced in the areas where the surface treatment is being applied.
Please note that the Bus Rapid Transit (BRT) project will be continuing work on the bus stations within the University Ave. project limits. The BRT project’s ongoing work may require periodic lane closures or other traffic restrictions.
Traffic/Pedestrian/Bike Impacts
Traffic will remain in a configuration that maintains at least two lanes in both directions during peak travel periods on University Ave. within the project limits (from approximately Shorewood Blvd. to University Bay Dr.). Short-term sidewalk detours along University Ave. and adjacent side streets may be needed to complete the remaining sidewalk and pedestrian ramps. Please be alert for sidewalk closed and pedestrian detour signage that will be in place while this work is being completed. Also note that the Bus Rapid Transit (BRT) project is utilizing single-lane closures east and west of the University Ave. project limits. additional information on work related to the BRT project can be found here: https://www.cityofmadison.com/metro/routes-schedules/bus-rapid-transit
Note that the work is weather dependent and may be subject to change.
View the full University Avenue Weekly Update.
View past project updates »Project Details
Project Information
Project Overview
University Ave is scheduled for reconstruction from Shorewood Boulevard/Hill St to University Bay Drive/Farley Ave. The City of Madison is jointly participating with the Village of Shorewood Hills on the design and construction. The project includes reconstruction of pavement, curb and gutter, sidewalk as necessary, street lighting, traffic signals, water main, sanitary sewer and storm sewer. Alternatives to improve pedestrian & bicycle connectivity, bus rapid transit initiatives and stormwater drainage have been reviewed, and the project plans have been updated to include a new pedestrian & bike overpass of University Bay Dr., a widened sidewalk along the southerly side of University Ave., and a 96-inch storm sewer pipe to help improve drainage in the area. The project continues to be coordinated with the City’s planning efforts for bus rapid transit.
Full Project Map
Typical Section Example
University Bay Overpass Alternative
Project Fact and Details Sheet
View a larger image of proposed improvements
Project Limits
Shorewood Boulevard/Hill St to University Bay Drive/Farley Ave.
Project Schedule
Construction is scheduled for 2022.
Public Involvement
There are a number of points of contact during this project where the public is encouraged to give feedback as part of public information meetings and public hearings. Dates and times are indicated below:
Public Information Meetings
- March 11, 2021 Public Information Meeting PowerPoint Presentation
- March 11, 2021 Public Information Meeting Recording
- Univ Ave (Shore-Univ Bay Dr) Roll Plot Exhibit
- Dec. 18, 2019 Public Information Meeting PowerPoint Presentation
- Dec. 18, 2019 Public Information Meeting Display Photo
- June 13, 2019 Public Information Meeting PowerPoint Presentation
- June 13, 2019 Public Information Meeting Preliminary Plan Overview
- The residents and businesses impacted by the University Avenue project are welcome to attend a monthly coordination meeting to discuss the University Avenue construction project. The coordination meeting will be held on the second Wednesday of each month at 11 a.m., 3230 University Avenue, Suite No. 7. The first meeting was held June 8, 2022. Integrity Grading and Excavating will give a construction schedule update at each meeting followed by an open platform for any questions and/or concerns with the ongoing construction operations.
City Meetings, Process
Board of Public Works: June 16, 2021
Transportation Commission: April 15, 2020
Common Council: July 6, 2021
Mailings
Extension of work hours for Construction Activities (Starting around Aug. 15, 2022)