Construction Closures
East Washington Avenue - Segment 4
|
| Date: |
1/19/2009 - 12/1/2009 |
Impact: |
Major |
| Location: |
East Washington Avenue (Marquette Street to Melvin Court)
HWY 30/Aberg Avenue (McCormick Avenue to Fair Oaks Avenue) |
| Contract No: |
6339
|
| Metro Detour: |
20 (Informational Link)
OUTBOUND Route 20 stops on Shopko Dr. near Copps will be closed all day Saturday, March 28.
Due to construction progress, this detour may also run Sunday, March 29 from 7:30 AM - 12:30 PM. 266-4466; mymetrobus@cityofmadison.com--->
OUTBOUND Route 20 stops on Shopko Dr. near Copps will be closed all day Saturday, March 28. Due to construction progress, this detour may also run Sunday, March 29 from 7:30 AM - 12:30 PM. 266-4466; mymetrobus@cityofmadison.com
|
| Details: |
Here's the planned work for the week of November 9th for East Washington Avenue (Marquette Street to Melvin Court) and HWY 30/Aberg Avenue (McCormick Avenue to Fair Oaks Avenue)
East Washington Avenue Electrical work Landscaping Pavement marking HWY 30/Aberg Avenue Landscaping Electrical work Concrete barrier wall installation Pavement marking Bus stops will be maintained in the construction zone, See Metro website or project website - 'Metro Transit During Construction' for details. The field office phone is (608) 204-9000 The project website: http://www.eastwashington.org
|
|
|
More Information »
|
Hoepker Road
|
| Date: |
7/20/2009 - 11/7/2009 |
Impact: |
Major |
| Location: |
Hoepker Road (700' West of American Parkway - Triumph Drive |
| Contract No: |
6265
|
| Details: |
Hoepker Road (700' West of American Parkway - Triumph Drive): Road will be closed to through traffic. Access to businesses along Hoepker Road will be maintained at all times. Project is expected to last until November 7.
Note: American Parkway is closed at Hoepker Road.
The street improvements will consist of widening the road to four lanes with bike lanes, installing medians with turn lanes and installing curb and gutter. Storm sewer and street lighting will also be added.
Additional information about these and other projects is available on the City's Road Works website at www.cityofmadison.com/transportation/roadworks.
|
|
|
More Information »
|
American Parkway
|
| Date: |
8/7/2009 - 11/7/2009 |
Impact: |
Major |
| Location: |
American Parkway at Hoepker Road |
| Contract No: |
6265
|
| Details: |
American Parkway (Hoepker Road Intersection): The intersection of Hoepker Road and American Parkway will not be passable and motorists should avoid the intersection. Project is expected to last until November 7.
The street improvements will consist of widening the road to four lanes with bike lanes, installing medians with turn lanes and installing curb and gutter. Storm sewer and street lighting will also be added.
Additional information about these and other projects is available on the City's Road Works website at www.cityofmadison.com/transportation/roadworks.
|
|
|
More Information »
|
Femrite Drive Reconstruction
|
| Date: |
8/25/2009 - 11/14/2009 |
Impact: |
Major |
| Location: |
Femrite Drive (I-90 Overpass - Meier Road) |
| Contract No: |
6026
|
| Details: |
Project consists of widening Femrite Drive by adding bike lanes and in some areas a left turn lane.
Femrite Drive will be open to local traffic only within the phase under construction.
Phase 1: I-90 Overpass to Omeda Drive. This phase has been completed. Motorists should access this section from the west.
Phase 2: Ohmeda Drive - Meier Road. This phase started 9/21 and is expected to last until 11/14.
Additional information about these and other projects is available on the City's Road Works website at www.cityofmadison.com/transportation/roadworks.
|
|
|
More Information »
|
Lower Badger Mill Creek Lift Station and Sanitary Sewer Force Main
|
| Date: |
10/5/2009 - 11/18/2009 |
Impact: |
Major |
| Location: |
Midtown Road (Hidden Hill Drive- Meadow Road) |
| Contract No: |
6329
|
| Details: |
Midtown Road will be closed to all traffic between Hidden Hill Drive and Meadow Road from October 5 to November 19.
Project includes the installation of a new sanitary sewer force main.
Additional information about these and other projects is available on the City's Road Works website at www.cityofmadison.com/transportation/roadworks.
|
|
|
More Information »
|
Starkweather Ped Bridge over Aberg Ave
|
| Date: |
11/15/2009 - 11/15/2009 |
Impact: |
Major |
| Location: |
Aberg Avenue (East Washington Ave. to Shopko Ave.) |
| Contract No: |
6177
|
| Details: |
All lanes of Aberg Avenue from East Washington Avenue westerly to Shopko Avenue will be closed on Sunday November 15, from 7:00 a.m. to 11:00 a.m. The closure is due to the setting of trusses for the Starkweather Path Pedestrian Bridge over Aberg Avenue.
Shopko Avenue businesses may be accessed from Packers Avenue via Aberg Avenue, just west of Shopko Drive.
Questions regarding the road closure may be directed to City Engineering Division, at (608) 266-9219.
|
|
|
More Information »
|
|